Contractors Short-Listed for Purple Line

WEDNESDAY, MARCH 10, 2021


Last week, Purple Line Transit Partners, the private consortium overseeing the construction of the Purple Line light-rail project in Maryland via a public-private partnership, announced that three design-build contractors were short-listed to complete the project.

According to PLTP, the bidders were narrowed down from five teams that had expressed interest in the project.

Short List, Next Steps

The following contractors have been short-listed for the Purple Line light-rail project:

  • Halmar International;
  • Maryland Transit Solutions (a team of Dragados USA and OHL USA); and
  • Tutor Perini and Lunda Construction Co., a joint venture.

“PLTP short-listing three qualified firms represents the next step in moving the Purple Line forward,” said Greg Slater, Maryland Department of Transportation Secretary, in a press release. “MDOT is committed to successfully delivering this important transit project for the citizens of Maryland, and we appreciate PLTP’s continued partnership to make this a reality.”

A request for proposals is slated to be issued in mid-March, with hopes of awarding a contractor by June, prior to a financial agreement being completed in September. Once a final agreement is reached, the winning construction team would resume major construction.

However, it could take several months to mobilize workers and heavy equipment.

“Collaborating closely with our MDOT and MTA (Maryland Transit Administration) partners, we look forward to rapidly bringing on a new contractor and resuming full-scale construction,” Jane Garvey, the chair of PLTP, said in the release.

Project officials report that a new opening schedule will be determined as part of the new construction contract. Originally, the light rail was scheduled to open to the public by March of next year, however, the previous contractor reported that it wouldn’t be able to carry passengers until late 2024.

In the meantime, MDOT has taken over subcontracts to continue work such as moving utility lines and manufacturing the light-rail vehicles.

Purple Line Saga

According to Maryland Department of Transportation and the Maryland Transit Administration, the Purple Line is a 16-mile light rail project that will run from Bethesda, in Montgomery County, to New Carrollton, in Prince George's County, eventually providing a direct connection for Metrorail Red, Green and Orange Lines; at Bethesda, Silver Spring, College Park and New Carrollton. The project will also connect with MARC, Amtrak and local bus options. The Purple Line will be powered by a catenary system.

Owned by MDOT and the MTA, plans began with assessments in 2002-08, followed by a draft environmental impact study and light rail being selected as transportation. The FTA issued the final record of decision in 2014, followed by Purple Line Transit Constructors—a partnership consisting of Fluor (Irving, Texas), Lane Construction Corp. (Cheshire, Connecticut) and Traylor Bros Inc. (Evansville, Indiana)—being chosen in 2016 to assist with the project.

Through the public-private partnership, PLTC agreed to work on the design, build and operate, as well as maintain the system for 35 years. Other teams collaborating on the project at the time included: the Washington Metropolitan Area Transit Authority, Montgomery and Prince George's counties, the Maryland-National Capital Park and Planning Commission, Maryland Department of Transportation State Highway Administration and local municipalities.

In March 2019, a judge cleared a lawsuit that might have brought construction to a halt. A few months later, in September, officials announced noted that the line would open in phases, starting in Prince George’s County, where the first stations would open. At the time, trains were being built in New York and planned to arrive for testing in 2021.

By October, WTOP News reported that issues with concrete at a Maryland Metro entrance shaft, labeled defective by the state, were just one of many issues plaguing the project after the outlet had requested documentation on the project.

According to the documents, in 2016 and 2017, more than one instance of 47 oversight reports where contractors were traversing private property without necessary permission and traffic safety issues. While more minor issues were easily resolved, there were also instances where construction was commenced without the proper approvals, such as in July 2018, when designs were returned with a request for revisions, but construction still began two weeks later.

In December, problems identified with the concrete included: cracks in approach slabs, concrete out of tolerance, pockmarks and footprints. The sidewalk has issues with “honeycombed sections, voids and does not meet the minimum cover requirements for welded wire reinforcement,” according to the report.

By October 2020, corrective work was slated for completion by the summer, with the interior build-out commencing by the end of 2021. At the same time, project officials expected the project to reach completion in April 2023, though those involved with the project emphasized that they were still aiming for the end of 2022.

Regarding PLTC leaving the project, Washington Business Journal reported that the state's transportation agencies said in a statement that the Purple Line has experienced delays "in conjunction with litigation" since 2016 and have been "actively engaged in discussions to mitigate the impacts of litigation and change order requests on both the project schedule and costs."

In April, PLTC requested an additional $187.7 million and five extra months to complete work regarding a required “crash wall” slated to go between a portion of the Purple Line and CSX freight tracks.

The following month, PLTC announced that it planned to withdraw from the project as a result of a three-year ongoing dispute with MDOT and the MTA over extensive delays and cost overruns. However, PLTC reported that its other consortium, Purple Line Transit Partners (Meridiam, Fluor and Star America Infrastructure Partners) had agreed to take over the project.

According to reports, PLTP also held a public-private partnership with the state of Maryland for a larger design-build and operating contract, worth $5.6 billion. In its release, PLTC said it would be exercising a clause in the design-build agreement which allowed for withdrawal if total project delays reached 365 days. However, according to the Washington Post, the project was already approaching 1,000 days’ worth of delays from various legal battles, right-of-way acquisition and design changes.

In June, the PLTP formally notified state transportation agencies that it intended to terminate the partnership in 60 days, citing more than $800 million in cost overruns. Two months later in August, Baltimore Circuit Court Judge Jeffrey M. Geller filed a temporary restraining order that prevented PLTP from walking off the project.

At the beginning of September, Geller ruled that the joint venture could quit over the cost overrun dispute, though transit officials could attempt to salvage the partnership. By the end of the month, construction came to a halt, as PLTP proceeded with its decision to depart from the endeavor.

Following the court’s decision, Maryland transportation officials planned to take over day-to-day management of the project but were still making efforts to come to a settlement with PLTP. Should the JV stick with its plans to leave, state officials estimated the decision would add another one to two years of delays to the project, which is already two and a half years behind schedule.

In November, MDOT announced that it had agreed to pay an additional $250 million to the remaining companies that have agreed to manage construction of the delayed and cost disputed Purple Line project in an effort to salvage the 36-year, $5.6 billion PLTP partnership.

The settlement amount was reported to cover what PLTP and its associated construction team spent on a lawsuit filed by project opponents and the state’s delay in providing right of way.

Originally made up of primary construction contractor Fluor, and infrastructure investors Meridiam and Star America, despite the settlement, Flour announced that it would still be leaving the partnership, having quit last month over delays and cost escalations.

According to The Washington Post, the deal revived one of Hogan’s signature transportation projects and a public-private partnership that imploded in September following three years of cost disputes.

Until a new design-build contractor replaces Flour, MDOT said at the time that it would oversee subcontractors on a variety of work to keep the project moving, such as paving, moving utility lines and manufacturing light-rail vehicles, among others.

The settlement was sent to the state’s Board of Public Works in December.

Most recently, in January, the Maryland Board of Public Works, comprised of Gov. Larry Hogan, Comptroller Peter Franchot and Treasurer Nancy K. Kopp, unanimously approved a $250 million legal settlement to resume construction on the Purple Line project.

PLTP is making additional efforts as a means to keep costs low and prevent further delays. Some of the efforts include exploring ways to expedite the remaining work and reducing its internal rate of return from the project by 20%.

Regarding Flour, the prior contractor and its construction partners received $100 million before the end of 2020, with the state intending to pay the remaining $150 million within 12 months, after the contractor has been replaced and a new agreement is signed between it, the state and PLTP.

As part of the settlement, Meridiam and Star America have agreed to spend up to an additional $50 million to keep construction moving until a new contractor is on board.

   

Tagged categories: Contractors; Department of Transportation (DOT); NA; North America; Ongoing projects; Program/Project Management; Project Management; Rail; Transportation