MSG Reveals Sphere Roof Completion Plan

Wednesday, October 20, 2021

Comment | More

Earlier this month, project leaders announced that construction on the domed roof of the $1.8 billion Las Vegas MSG Sphere was expected to reach completion this fall.

The news arrives just months after construction crews held a “topping out” ceremony to celebrate the completion of the globular venue’s steel frame. At the time, work was being carried out to build the exosphere framework for the 580,000 square feet of lights.

Project Background

The project broke ground in September 2018, as a collaboration between the Madison Square Garden Company and Las Vegas Sands Corp., along with designs from Populous.

The technology behind the 350-foot-tall, 500-foot-diameter sphere was originally unveiled in February 2018.

Officials at the time touted “beamformed” technology for the sound transmission—enabled by thousands of tiny speakers embedded into the venue walls—that will give the same sound clarity for people in the back as the people in the front.

The sphere’s interior will have a digital display plane of a 170,000 square feet, and its exterior counterpart, wrapped in an open-air trellis structure, will hold 580,000 square feet of programmable surface.

Inside, the display will be the largest and highest resolution LED display plane in the world, according to officials.

Madison Square Garden Company

Earlier this month, project leaders announced that construction on the domed roof of the $1.8 billion Las Vegas MSG Sphere was expected to reach completion this fall.

Gov. Brian Sandoval touted some other numbers at the groundbreaking, including the estimated 3,500 construction jobs and 4,400 permanent jobs at the site. Once the sphere is complete, it is expected to bring $730 million in annual economic impact and $48 million in estimated tax revenue. MSG selected AECOM as the general contractor in June 2019.

As mentioned, in February of last year, the world’s fourth-largest crawler crane arrived onsite from Belgium. The crane, dubbed the DEMAG CC-8800, can extend 580 feet high and weighs 869 tons. The crane can also rotate 360 degrees.

After being shipped across the Atlantic Ocean, it reportedly took 120 tractor-trailers to deliver the crane and then 18 days to assemble it.

On top of the crane’s weight, 850 tons of counterweight have been added for stability.

In August 2020, officials confirmed a new construction schedule for the DEMAG, which included three main tasks: superstructure concrete work, structural steel and the building of the steel-domed roof.

In October 2020, MSG Entertainment confirmed that a pair of steel girders (a combined 240 tons) were put it place earlier that month. The girders span the length of the venue’s stage and will support the structure’s 13,000-ton steel-domed roof—the heaviest lift of the project.

The two girders were reportedly formed by placing two pairs of 100-ton steel tubs on top of one another. The bottom halves of each girder were set in place at the end of September 2020 by the crawler crane.

After that, concrete was pumped to the bottom of the tubs, followed by another tub lifted into place, creating a hollow cavity. To finish, the cavities will be filled with more concrete. These girders and concrete are vital to the structure’s foundational support.

At the end of last year, some contracts on the project shifted, as MSG Entertainment Co. announced that it was taking over construction management duties from general contractor AECOM.

According to reports, AECOM had transitioned from its role as general contractor with a new services agreement that facilitates involvement with the Sphere through the project’s completion.

The project now falls under the guidance of new President of Development and Construction at MSG, Jayne McGivern, who has assembled a team of professionals for the project.

“We have taken significant steps to strengthen our internal construction team,” McGivern said in a statement at the time. “This, along with valued support from AECOM, will give us greater transparency and control over the construction process while enabling us to continue benefiting from AECOM’s expertise. MSG Sphere will be a venue unlike any other, and we believe we are well-positioned to not only advance our Las Vegas project, but also deliver on our long-term vision for MSG Sphere.”

In late February, construction of the Sphere reached a milestone with the completion of the 100-foot-diamter steel ring at the top of the structure.

In order to position the giant piece, crews reportedly spent almost a month assembling it on the ground before using the DEMAG CC-8800 crane to hoist it into place.

Crews used a hydraulic lift to calibrate the ring’s exact position before roof trusses were put in place.

Roof Timeline

According to the Las Vegas Review-Journal, construction crews completed the installation of metal decking and rebar atop the skeletal dome at the end of last month. Since then, a spokesman for Madison Square Garden Entertainment Corp. told reporters that workers were pouring roughly 13,000 tons of concrete to fill out the structure.

Most recently, crews were reported to be almost finished with installing insulated metal paneling wrapping around the project’s exterior facade. Paneling along the lower hemisphere had also been completed.

Additional ongoing work on the project includes affixing sheet metal to the insulated metal, as well as installing the insulated paneling along the top half.

The spokesman added that officials expect the steel exosphere to reach competition in 2022 and plans to host a second “topping out” ceremony.

Project leaders plan to finish over the next year the roof concrete, the venue’s exterior facade and continue building out the interior and a pedestrian bridge. The project is still eyeing up completion in 2023.

When completed, the MSG Sphere will stand 366 feet tall and the building will be 516 feet wide at its widest point. By comparison, the nearby Palazzo tower is 642 feet high, The Venetian is 475 feet tall and the High Roller observation wheel is 550 feet tall.

   

Tagged categories: Color + Design; Commercial Construction; Design; NA; North America; Ongoing projects; Project Management; Projects - Commercial; Public spaces

Comment Join the Conversation:

Sign in to our community to add your comments.


Advertisements
 
Axxiom Manufacturing

 
Strand’s Industrial Coatings

 
Sauereisen, Inc.

 
Tarps manufacturing, Inc.

 
CRW

 
HoldTight Solutions Inc.

 
KTA-Tator, Inc. - Corporate Office

 
Abrasives Inc.

 
EDCO - Equipment Development Co. Inc.

 
 
 

Technology Publishing Co., 1501 Reedsdale Street, Suite 2008, Pittsburgh, PA 15233

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy Policy   |   Terms & Conditions   |   Support   |   Site Map   |   Search   |   Contact Us