$3.9B Deal Reached for JFK Terminal 6

Thursday, August 5, 2021

Comment | More

On Tuesday (Aug. 3), the Port Authority of New York and New Jersey announced that it had reached an agreement with JFK Millennium Partners (including JetBlue Airways) to build the new international Terminal 6 at JFK International Airport.

The project was initially supposed to break ground in 2020, but investment came into question after the COVID-19 pandemic. The restructured deal is reportedly a major step forward for the JFK project.

Subject to Board approval, the Port Authority will finalize and enter into a lease agreement with JMP for the construction of the $3.9 billion, 1.2 million-square-foot terminal. The full $3.9 billion expense of building the terminal will be privately financed by the JFK Millennium Partners consortium.

The terminal is slated to be built on the sites of the former Terminal 6, which was demolished in 2011, and the aging Terminal 7, which will be torn down after British Airways relocates to Terminal 8.

travelviews / Getty Images

On Tuesday (Aug. 3), the Port Authority of New York and New Jersey announced that it had reached an agreement with JFK Millennium Partners (including JetBlue Airways) to build the new international Terminal 6 at JFK International Airport.

The new terminal will connect to Terminal 5 and be equipped with capacity for 10 new gates, as well as check-in halls, arrival spaces and more than 100,000 square feet of commercial dining and retail amenities, lounges, and recreational spaces.

Construction of the new terminal is scheduled to begin in mid-2022 and the first new gates are scheduled to open in 2025.

According to the governor’s office, the development of Terminal 6 is expected to result in over 4,000 direct jobs and direct payroll wages of $1.9 billion. The total economic activity impact from the project, including indirect effects such as the local market participation of employees of suppliers, amounts to nearly $2.8 billion in total wages and $6.3 billion in total economic activity.

JFK Redevelopment Plan History

Initially unveiled in January 2017, the revamp plan for JFK revealed eight terminals to combine into one unified airport with the terminal complexes on the north and south sides. In addition, airport amenities, ground transportation and roadways are also set to improve. Overall, the airport’s capacity is estimated to increase by 15 million passengers a year.

“This historic investment to modernize JFK Airport and the surrounding transportation network will not only ease travel through this major hub, but it will ensure JFK joins the ranks as one of the finest airports in the world,” said Cuomo at the time.

By October of that year, a team was tapped for the extension, led by United Kingdom-based firm duo Mott MacDonald and Grimshaw Architects, which is responsible for spearheading airport redesigns in London, South Korea, Hong Kong, Singapore, Zurich, Germany, the Netherlands, Canada, Australia and South Africa.

The team also includes: TranSolutions, Harris Miller Miller & Hanson, VJ Associates, ACB Architects, EnTech Engineering, Naik Consulting, Reichman Frankle and Holmes Keogh.

A year later, Cuomo announced that the new $7 billion, 2.9 million-square-foot terminal on the airport's south side would be developed by the Terminal One Group, a consortium of four international airlines—Lufthansa, Air France, Japan Airlines and Korean Air Lines. The initial plans called for replacing JFK's Terminal 1 and Terminal 2 as well as the area left vacant when Terminal 3 was demolished in 2014. It would also be connected to the existing Terminal 4.

On the north side, the proposed new $3 billion, 1.2 million-square-foot terminal would be developed by JetBlue, which planned to demolish Terminal 7 and combine it with the vacant space where Terminal 6 was demolished in 2011. This would connect to the airline's existing Terminal 5.

New passenger facilities would also feature larger waiting areas with high ceilings, natural light and modern architecture coupled with interior green space, exhibits and art featuring iconic New York landmarks and local artists, according to officials at the time.

In July 2019, the Port Authority issued requests for the development of the new Kennedy Central Hub. The 14-acre mixed-use development will serve as a commercial and recreational epicenter for airport visitors, travelers and employees.

The RFPs for that project are anticipated in the second quarter of this year.

At the end of October, the authority approved an investment of approximately $4.5 billion for three of its major projects, including $445 million for the JFK reno. As a whole, the JFK project is expected to be achieved through a public-private partnership, in which 90% of will be covered by private funds.

In February, Cuomo announced that the Port Authority of New York and New Jersey reached an agreement on terms with Delta Air Lines for work on JFK International Air Terminal’s Terminal 4—a $3.8 billion renovation project.

The work is for the expansion and renovation of Terminal 4 originally included the addition of 16 new gates (500,000 square feet), the renovation of existing concourses and roadway upgrades.

Most recently, in May, the Board approved an agreement on key terms for an amended plan for the JFK International Airport. The terms were with Delta Air Lines and JFK to expand Terminal 4 and consolidate Delta operations.

The now $1.5 billion project, which is being financed by private capital, was initially authorized in February 2020 as a $3.8 billion expansion and modernization plan. However, due to the impact of the COVID-19 pandemic, the plan has been reduced by about 60% to highlight key priorities.

Delta currently operates out of both Terminal 4 and Terminal 2, and this expansion aims to allow Delta to offer a seamless travel experience by consolidating all of Delta's JFK operations into Terminal 4.

The project will modernize and expand the existing terminal by about 150,000 square feet and will replace the 11 gates currently used at Terminal 2, which was built in 1962. That terminal will then be demolished.

The expansion and renovation at Terminal 4 is slated to break ground later this year, enabling Delta to consolidate its operations in late 2022, with full project completion in late 2023. A contractor for the project has not been released.

   

Tagged categories: Airports; Good Technical Practice; JFK International Airport; NA; North America; Ongoing projects; Renovation; Terminals

Comment Join the Conversation:

Sign in to our community to add your comments.


Advertisements
 
HoldTight Solutions Inc.

 
Tarps manufacturing, Inc.

 
Seal for Life/STOPAQ

 
Sauereisen, Inc.

 
Axxiom Manufacturing

 
CRW

 
Abrasives Inc.

 
KTA-Tator, Inc. - Corporate Office

 
 
 

Technology Publishing Co., 1501 Reedsdale Street, Suite 2008, Pittsburgh, PA 15233

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy Policy   |   Terms & Conditions   |   Support   |   Site Map   |   Search   |   Contact Us