Coatings Industry News

Main News Page


Skanska Worker Killed on Pensacola Bridge

Friday, May 7, 2021

Comment | More

At the end of last month, a deadly accident was reported at the Pensacola Bay Bridge, involving a Skanska employee being struck by a subcontractor’s dump truck on the work site.

Local police authorities have identified the victim as 61-year-old Mark Carter, of Pensacola, Florida.

“We are deeply saddened by the loss of our team member, and our thoughts and prayers are with the family and loved ones,” Skanska said in a statement. “We are also focused on providing support to our workers on the project.”

What Happened

According to the company, at approximately 3:30 p.m. on April 28, the Skanska construction worker was fatally struck by a dump truck between the main bridge and 17th Avenue overpass at the Pensacola Bay Bridge project site.

The dump truck is owned by one of the company’s subcontractors and, at the time, was hauling asphalt. The driver is currently being investigated and the victim’s family has also reportedly opened a case into the matter.

Skanska reports that the company is fully cooperating with local authorities and will also be conducting an internal investigation.

“We want to thank the local authorities for their rapid response. We are also focused on providing support to our workers on the project. The jobsite has been secured and work is temporarily suspended.”

At this time, no one has been charged for the incident.

Work on the project has since been restarted while the investigation is ongoing.

Replacement Project History

The Pensacola Bridge replacement project kicked off back in 2016 as the original structure—constructed in 1960—was reaching the end of its lifespan. The project consists of a new U.S. 98 bridge across the bay between Pensacola and Pensacola Beach comprised of two separate structures: one for eastbound traffic, the other for westbound, with three 12-foot travel lanes, a 10-foot-wide path for foot and bicycle traffic, as well as 10 feet inside and outside shoulders. Pedestrians will be able to use shaded observation areas to take in views of the bay.

The first new bridge reached completion in 2019. At that time, two lanes of eastbound and two lanes of westbound traffic were slated to be moved onto the new bridge. Once that is complete, crews plan to demolish the old bridge and build the second structure by late 2021.

The $430 million replacement project is being funded by FDOT and is reported to be the state’s largest-ever transportation project.

Bridge vs. Barge

In anticipation that Hurricane Sally would make landfall some 200 miles west of Pensacola, contractor and design-build team Skanska USA hadn’t planned to move its construction equipment but told Engineering News-Record that it had made all appropriate pre-storm preparations. However, when Hurricane Sally unexpectedly changed her course in the final hours of approaching land, it was too late to take additional action.

As a result, the Category 2 hurricane landed just 30 miles west of the Pensacola Bay Bridge (also known as the Three Mile Bridge) replacement project site, causing the dislodge of several barges and other construction equipment.

One of the worst impacts, Pensacola News Journal wrote at the time, was a crane that passed under the Three Mile Bridge, smashing through the surface of the road from beneath, destroying the span. While the structure was closed immediately following the barge impact on Tuesday morning, it was reported that the bridge suffered a second impact the following day. Upon preliminary damage assessments, FDOT has determined that at least five of the 105 spans are irreparable and will have to be reconstructed.

The Garcon Point Bridge was also affected by a dislodged barge and was also closed.

A few days later, however, inspectors discovered that damages to the Pensacola Bay Bridge were worse than previously expected. During a preliminary inspection, crews found that:

While FDOT’s statewide team of bridge experts are nearing conclusions of further inspection and assessments of the structure, they released additional information on the experienced damages. At the time, the Department reported that a survey of the piers and topside inspections were completed along with most of the underwater footings. Further inspection findings included the inspection of 202 underwater footings, while top side inspection teams assessed 105 spans, 202 piers and 525 beams; FDOT identified five spans requiring full replacement, in additional to two that would require partial replacement; and that a number of beams will require replacement, however, that number was still being determined.

At the beginning of October, FDOT announced that demolition efforts on the damaged areas of the Pensacola Bay Bridge had begun, with focus on areas that need cleared for dive access in order to examine the final 22 footings below the waterline.

At the time, three of Skanska’s barges remained on or under the structure, and would have to be removed with great caution.  In wake of the efforts taken to repair the structure, Skanska fabricated 25 beams, various piers and other replacement beams and piers at its offsite yard needed to begin repair efforts. The contractor also reached out to other facilities to assist in production.

By the end of the month, FDOT issued a letter of intent to Skanska USA seeking damages and lost toll-related revenue because of the current toll suspension on the Garcon Point Bridge. However, according to Sen. Doug Broxson, lost toll revenue caused by emergency closures are usually paid out by the Florida Legislature. In terms of tolls revenue, Broxson added that the loss was a monthly difference of between $700,000 and $4 million.

Additionally, lawsuits regarding the construction company and affected local businesses are still ongoing within the court system.

Originally, Gov. Ron DeSantis ordered the suspension of tolls on the Garcon Point Bridge to last until Nov. 13. This toll suspension has since been extended to April 9, though officials have said they are confident those tolls will remain suspended until traffic is fully open on the Pensacola Bay Bridge.

Providing a repair update at the beginning of December, Florida Rep. Alex Andrade, R-Pensacola, told the Pensacola News Journal that Skanska still had barges littered around the area, alongside crews accounting for safety, equipment, and fuel, which in turn is driving up enormous daily costs.

While Skanska did not attend the town hall, the company has since been reported to have hired two subcontractors to initiate repairs on the bridge. In their efforts, the teams have been sending divers to evaluate pilings and repair concrete, in addition to replacing entire spans of the bridge.

Regarding the cost of the additional repairs, Skanska or its insurance companies are slated to pay for the repairs directly. Although many sections of the structure are being repaired ahead of schedule, the company is motivated to complete the project as soon as possible as its reported to be “building at a loss.”

At the end of March, officials from the Florida Department of Transportation announced that traffic on the Pensacola Bay Bridge was scheduled to reopen the week of Memorial Day. Once a connection is restored between Pensacola and Gulf Breeze, Skanska will remain working on site through until January of 2022 to complete all improvements to the new bridge.

Skanska Seeks Liability, Cases Build

In five separate filings—each representing a different barge—Skanska requested in January that the courts declare the company not liable “for any loss, injuries or damages" related to barge damage, including economic losses suffered by businesses from the closure of the new span of the bridge.

While a Skanska spokesperson told reporters at the time that the company doesn’t comment on active or pending litigation, should the courts refuse the company’s request, they’ve also submitted an alternate request, asking that the liability be limited to the dollar amount of its ownership in each vessel.

Skanska has valued its barges to each cost between $125,000 and $550,000, totaling $1.43 million, and asks that they be divided pro rata between all those submitting valid claims within a certain time period to be determined by the court. A copy of a security bond equal to the value of each barge was included with each filing.

At the time, numbers on the demolition and repair activities included:

  • Seven fully damaged spans removed;
  • Eight partially damaged spans removed;
  • 16 damaged pedestrian path beams removed;
  • 61 damaged I-beams removed, with eight replaced;
  • Four damaged trophy pieces removed; and
  • 11 replacement piles driven.

Over the course of the work, FDOT is continuing to monitor Skanska’s investigation with state and local authorities to determine if the line connecting the barge to the sea floor was severed, as another barge was reported to break loose at the end of December.

In more recent reports, the number of claims by plaintiffs seeking compensation from Skanska for allegedly harming their businesses has risen to nearly 1,000. Monday was the deadline for businessowners and residents who have been impacted by the bridge's outage to file suit, according to the Pensacola New Journal.

The claimants range from business owners to even commuters in the Gulf Breeze and Pensacola areas, but spread as far as Escambia and Santa Rosa counties. The newspaper added that more filings may be added in the next week relating specifically to cases with damaged personal property as that has a different deadline.

   

Tagged categories: Accidents; Bridges; Bridges; Construction; Contractors; Fatalities; Health & Safety; Health and safety; NA; North America; Ongoing projects; Program/Project Management; Project Management; Subcontractors; Transportation

Comment Join the Conversation:

Sign in to our community to add your comments.


Advertisements
 
Western Technology Inc.

 
Sauereisen, Inc.

 
Axxiom Manufacturing

 
HoldTight Solutions Inc.

 
PaintSquare

 
Tarps manufacturing, Inc.

 
Abrasives Inc.

 
KTA-Tator, Inc. - Corporate Office

 
 
 

Technology Publishing Co., 1501 Reedsdale Street, Suite 2008, Pittsburgh, PA 15233

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy Policy   |   Terms & Conditions   |   Support   |   Site Map   |   Search   |   Contact Us