Denver Airport to Pay $183M in Settlement

Thursday, March 26, 2020

Comment | More

Denver International Airport has announced that it has settled all claims with Great Hall Partners, the first that was originally contracted in the public-private partnership for the $1.8 billion airport renovation.

Officials have been working together since November, when Great Hall officially ended its run with the project.

Project Saga

In November 2017, the DIA proposed the addition of 39 gates in an expansion project, up from the airport’s original proposal of 26. At the time, the project was estimated to cost $1.5 billion and would be a P3 headed by Ferrovial Airports. The overall deal was slated to include a $650 million terminal renovation, which would be overseen by Saunders Construction over the course of four years. (Cost estimates for the actual expansion at the time were not yet available, however.)

A couple months later in January 2018, two subsidiaries of Hochtief, a Germany-based construction company, were announced as the companies to oversee the expansion. The companies, Turner Construction and Flatiron Construction, would be building two new hubs for the airport, with the capacity for three more, as well as 16 new gates and installing additional pavement.

ra-photos / Getty Images

Denver International Airport has announced that it has settled all claims with Great Hall Partners, the first that was originally contracted in the public-private partnership for the $1.8 billion airport renovation.

That summer, DIA would announce an official multi-year, multi-phase renovation timeline headed by Great Hall Partners with a budget of $650 million. The P3 also included 30 years of private oversight of expanded terminal concessions. A groundbreaking ceremony followed on July 12, 2018.

However, first delays struck in February 2019 when concrete on the main floor was found to be weaker than expected. According to officials, early testing of the concrete’s compressive strength was lower than what the project’s plan specified, so the area followed up with intensive testing. The DIA also noted that the testing needed to be complete prior to cranes going onto the main floor to erect steel.

At the time of the discovery, preliminary estimates stated that the project could be delayed by 209 workdays—roughly 10 months total.

In July, GHP reported that the renovation of Jeppesen Terminal wouldn’t be complete until at least 2024, three years behind its 2021 deadline. The companies (Ferrovial Airports, Saunders Construction and JLC Infrastructure) claimed the delay was due to various airport-requested design changes and structural issues found in old concrete initially used for the airport’s construction.

However, Channel 4 CBS Denver claimed that the project’s full completion could extend to 2025—with costs projected to increase by nearly 50%, or $311 million.

Contract Saga

A month later, not long after DIA announced that it would be ending its P3 relationship with GHP for terminal renovations, the contractors released documents showing that the project requires more than $1 billion to complete.

Up $650 million from the original budget, the documents also claimed that various delays have pushed the completion date back to February 2024 as well.

According to a DIA-hired independent consultant, inspections revealed that no safety issues were present in the concrete. However, additional testing was recommended for alkali-silica reaction, known to cause swells, cracks and even weaken concrete. Traces of the ASR were later found in the terminal.

In October, Day presented a revised renovation budget totaling $770 million, which included the original budget and a $120 million contingency.

According to Day, subcommittees and steering groups were working to process the closing of GHP’s contract and settling associated claims so that the contractor could successfully vacate the property by Nov. 12. Although a 34-year concession deal was included in GHP's contract, Day also confirmed that the DIA will run that component themselves after the renovation is complete.

It was also noted that although the new $770 million budget failed to include GHP's termination fees, a report from Moody’s Investors Service shows that the airport has roughly $900 million in liquidity to back up any settlement.

Andy445 / Getty Images

Officials have been working together since November, when Great Hall officially ended its run with the project.

Later that month, the DIA announced that it had selected Hensel Phelps to serve as the preferred construction manager and general contractor for Phase 1 of the project previously held by GHP. Canada-based engineering company Stantec has been chosen as the preferred lead design firm for the entire project moving forward.

In addition, the DIA also selected Gilmore Construction, Sky Blue Builders and roughly another dozen subcontractors it hopes to take over from GHP to continue to aid in design, engineering, steel placement and electrical work. Those contracts totaled about $136 million.

Hensel Phelps was recently cleared to start construction, and will begin by finishing the project’s first phase, which includes finishing an expansion of upper-level balconies and construction of new airline check-in pods, bathrooms and escalators.

The end of the first phase is now slated to be complete in 2021. It was originally supposed to be finished last summer, but GHP only finished about 25% of the work.

The project’s full completion is now looking likely in 2024.

As of now, DIA officials say that the COVID-19 pandemic is not impacting construction work.

The Settlement

The Denver Post reports that the two reached a final settlement of $183.6 million.

The agreement, which is dated March 13, details more than $55 million in promised final payments on top of the $128.2 million previously reported.

The payments reportedly include compensation for Great Hall’s lenders, as well as breakage costs and costs to operate the site during the 90-day wind-down period that ended I November. About $38 million required by contract to cover the return on investment that Great Hall would have received from the project was also included in the settlement.

“We’ve been very transparent through this process and have met every milestone,” DIA said about the project in a statement. “This final payment means we can close the door on the past and move forward.”

   

Tagged categories: Airports; Contracts; Good Technical Practice; NA; North America; Ongoing projects; Terminals

Comment from Patrick Timpe, (3/28/2020, 1:08 PM)

Quite the usual cluster .... for projects of this size. Too many cooks in the kitchen on this project, plus someone or some bodies trying to do short cuts, i.e. poor concrete work; doing the work on the cheap. When will this type of story ever end??????


Comment Join the Conversation:

Sign in to our community to add your comments.


Advertisements
 
KTA-Tator, Inc. - Corporate Office

 
DeFelsko Corporation

 
SAFE Systems, Inc.

 
Fischer Technology Inc.

 
AWWA (American Water Works Association)

 
Tarps manufacturing, Inc.

 
Modern Safety Techniques

 
Sauereisen, Inc.

 
 
 

Technology Publishing Co., 1501 Reedsdale Street, Suite 2008, Pittsburgh, PA 15233

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy Policy   |   Terms & Conditions   |   Support   |   Site Map   |   Search   |   Contact Us