FIGG Fired from $800M Harbor Bridge Project

Monday, January 20, 2020

Comment | More

Earlier this month, the Texas Department of Transportation (TxDOT) requested that joint venture Flatiron-Dragados LLC replace the $800 million U.S. 181 Harbor Bridge replacement project’s designer, FIGG Bridge Engineers (FIGG).

According to reports, FIGG had overseen designs for the Harbor Bridge’s main spans—which are included in the cable-supported section of the bridge that will cross the Corpus Christi Ship Channel.

About the Project

Beginning in 2015, joint venture Flatiron/Dragados LLC was chosen by TxDOT for the design-build contract for the new Harbor Bridge, in Corpus Christi, Texas.

The new bridge is slated to carry U.S. Route 181 across the Corpus Christi Ship Channel off Corpus Christi Bay, replacing the current Harbor Bridge, a through arch bridge that was built in 1959. Once completed, the bridge will be the longest cable-stayed bridge in the United States.

TexasAndroid, CC-BY-3.0, via Wikimedia Commons

Earlier this month, the Texas Department of Transportation (TxDOT) requested that joint venture Flatiron-Dragados LLC replace the $800 million U.S. 181 Harbor Bridge replacement project’s designer, FIGG Bridge Engineers (FIGG).

According to TxDOT at the time, the total cost of the project—including the construction of the new bridge and the demolition of the current one—would be approximately $802.9 million.

In March 2017, construction activities began on the project, and by February 2019, crews had completed concrete placement on the first lift of the south tower.

The following month, Flatiron/Dragados LLC announced that the project would likely not meet its April 2020 completion deadline. However, the first span had been put into place on the north side of the ship channel, marking a significant milestone. Company officials attributed the delay to weather conditions and permitting issues.

Last month, on Dec. 16, a crawler crane collapsed on the construction site of the Harbor Bridge replacement project. No injuries were reported, however, a segment of Brownlee Boulevard had to be closed between Leopard and Winnebago Streets.

Investigators are currently working with project contractors, supervisors and subcontractors in order to determine what caused the incident. Flatiron/Dragados LLC spokesperson Lynn Allison adds that where the crane collapsed is only a small portion of the Harbor Bridge project and won’t impact the overall schedule.

National Transportation Safety Board Report

In addition to the project’s construction milestones and obstacles, TxDOT declared the suspension of design work for the Harbor Bridge project in November.

The announcement arrived after the National Transportation Safety Board released its findings related to the FIU bridge collapse in October, revealing that the probable cause was related to load and capacity calculation errors made by FIGG Bridge Engineers Inc.

FIU is home to the Accelerated Bridge Construction University Transportation Center, a multi-university center promoting ABC techniques. The pedestrian bridge was touted as an example of innovative design and construction meant to limit road closures and inconvenience stemming from the otherwise lengthy bridge construction process.

What’s Happening Now

“FIGG was shocked by Texas Department of Transportation’s press release concerning FIGG’s design role on the cable-stayed main span and relating this to the construction accident on a pedestrian bridge in Miami," FIGG said in a statement.

Due to the suspension and previous delays, the Harbor project’s original completion date slated for 2021, was pushed back to early 2023, increasing the project’s total to $930 million.

Although FIGG is reportedly certified by TxDOT in bridge design, complex bridge inspection and bridge construction management, among others, the department insists that NSTB’s opinions “were significant enough” for the decision to replace FIGG.

However, in receiving comments on the matter, FIGG disputed the decision, stating, “FIGG engaged Wiss, Janney, Elstner Assoc. Inc. (WJE), the preeminent forensic engineer in the nation, to review the Florida accident. WJE’s detailed research, in-depth analysis, and physical testing shows that faulty construction of the Florida bridge—which FIGG had no hand in—was to blame for the collapse, not its design.”

Currently, there is no indication on who will actually replace FIGG or how the process will affect the project’s timeline or budget. TxDOT reports that once a replacement is found, the new firm will review and recertify the existing design.

Editor's Note: This article was corrected at 3:40 p.m., Jan. 20, 2020, to correct the image used to represent the Harbor Bridge.

   

Tagged categories: Bridges; Bridges; Contractors; Contracts; Design build; Engineers; Infrastructure; Infrastructure; NA; North America; Ongoing projects; Program/Project Management; Project Management

Comment from Mark Taylor, (1/20/2020, 8:35 AM)

FIGG is just about radioactive at this point. After what happened in FIU and the determination that design was a major contributor to that bridge failure, the company's reputation is on shaky ground. Now this mess in Corpus Christi. Go back a couple years and you might remember the FIGG designed twin spans in Mt Pleasant, SC that suffered cable failures. Another bridge plagued with design issues.


Comment from Tony Rangus, (1/20/2020, 12:18 PM)

Legal Beagles rejoice. They are lining up at the legal trough.


Comment from Dan Savage, (1/20/2020, 3:25 PM)

This looks like a picture if the Sydney Harbor bridge?


Comment from Brandy Hadden, (1/20/2020, 5:40 PM)

Good catch, Dan!


Comment from Tom Schwerdt, (1/21/2020, 9:01 AM)

Dan, that's definitely the Corpus Christi Harbor Bridge in the photo, taken sometime not too long before the most recent repainting. The view appears to be from somewhere high on the aquarium building on the North side. I've walked/climbed all over that bridge. The linked photo below is of the aquarium from the bridge - note the blue gazebo in both photos: https://www.flickr.com/photos/corpuschristimpo/7545236314


Comment Join the Conversation:

Sign in to our community to add your comments.


Advertisements
 
KTA-Tator, Inc. - Corporate Office

 
DeFelsko Corporation

 
Tarps manufacturing, Inc.

 
Strategic Materials Inc.

 
SAFE Systems, Inc.

 
Sauereisen, Inc.

 
 
 

Technology Publishing Co., 1501 Reedsdale Street, Suite 2008, Pittsburgh, PA 15233

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy Policy   |   Terms & Conditions   |   Support   |   Site Map   |   Search   |   Contact Us