CO Airport Commits to $770M Budget

Wednesday, September 18, 2019

Comment | More

After the termination of the $1.8 billion private-public partnership contract with Great Hall Partners over the Jeppesen Terminal renovation at Denver International Airport, updates to the project’s budget and schedule have been revised.

Kim Day, CEO at DIA, explained through a presentation to the Denver City Council's Business, Arts, Workforce & Aviation Services Committee that the revised renovation budget totaled $770 million and included $120 million in contingency funds.

Renovation History

Roughly two years ago in November 2017, DIA proposed the addition of 39 gates in an expansion project, up seven from the airport’s original proposal of 26. At the time, the project was estimated to cost $1.5 billion and would be a P3 headed by Ferrovial Airports. The overall deal was slated to include a $650 million terminal renovation, which would be overseen by Saunders Construction over the course of four years. (Cost estimates for the actual expansion at the time were not yet available, however.)

A couple months later in January, two subsidiaries of Hochtief, a Germany-based construction company, were announced as the companies to oversee the estimated $700 million expansion. The companies, Turner Construction and Flatiron Construction, would be building two new hubs for the airport, with the capacity for three more, as well as 16 new gates and installing additional pavement.

© iStock.com / arinahabich

After the termination of the $1.8 billion private-public partnership contract with Great Hall Partners over the Jeppesen Terminal renovation at Denver International Airport, updates to the project’s budget and schedule have been revised.

That summer, DIA would announce an official multi-year, multi-phase renovation timeline headed by Great Hall Partners with a budget of $650 million. The P3 also included 30 years of private oversight of expanded terminal concessions. A groundbreaking ceremony followed on July 12, 2018.

However, first delays struck in Feb. 2019 when concrete on the main floor was found to be weaker than expected. According to officials, early testing of the concrete’s compressive strength was lower than what the project’s plan specified, so the area followed up with intensive testing. The DIA also noted that the testing needed to be complete prior to cranes going onto the main floor to erect steel.

At the time of the discovery, preliminary estimates stated that the project could be delayed by 209 workdays—roughly 10 months total.

In July, GHP reported that the renovation of Jeppesen Terminal wouldn’t be complete until at least 2024, three years behind its 2021 deadline. The companies (Ferrovial Airports, Saunders Construction and JLC Infrastructure) claimed the delay was due to various airport-requested design changes and structural issues found in old concrete initially used for the airport’s construction.

However, Channel 4 CBS Denver claimed that the project’s full completion could extend to 2025—with costs projected to increase by nearly 50%, or $311 million.

A month later, not long after DIA announced that it would be ending its P3 relationship with GHP for terminal renovations, the contractors released documents showing that the project requires more than $1 billion to complete.

Up $650 million from the original budget, the documents also claim that various delays have pushed the completion date back to February 2024 as well.

At the time of the announcement, DIA was reported to owe Great Hall Partners at least $200 million in reimbursements for the financing it provided for the start of the airport renovation project, a total termination fee was still being negotiated between the two.

According to a DIA-hired independent consultant, inspections revealed that no safety issues were present in the concrete. However, additional testing was recommended for alkali-silica reaction, known to cause swells, cracks and even weaken concrete. Traces of the ASR were later found in the terminal.

In concluding the recent events, Day has expressed to reporters that although the airport must go through another procurement process, she hopes to stay close to original budget, choosing to use a $120 million contingency fund. The project scope may face edits to meet the budgetary goals.

What’s Happening Now

In approving the use of contigency funds on the Jeppesen Terminal renovation, the project's budget has been increased from its orignal estimation of $650 million to $770 million.

According to Day, subcommittees and steering groups are working to process the closing of GHP’s contract and settling associated claims so that the contractor can successfully vacate the property by Nov. 12. Although a 34-year concession deal was included in GHP's contract, Day has also confirmed that the DIA will run that component themselves after the renovation is complete.

It is also noted that although the new $770 million budget fails to include GHP's termination fees, a recent report from Moody's shows that the airport is in a decent financial position to captivate those costs.

Currently, the DIA is also working to procure a new program manager, contractor and designers as well as working with airlines to modify the existing design. Day confesses that the process might result in the elimination of some concessions and other features but won’t be “taking away from the passenger experience." Still, all stakeholders at DIA will provide input to the final project features.

Replacement construction contracts and design teams are slated to be ready this fall, but no specific project delivery method has been specified at this time.

   

Tagged categories: Airports; Budget; Business management; Business matters; Business operations; Commercial Construction; Contractors; Contracts; Maintenance + Renovation; NA; North America; Ongoing projects; Partnerships; Project Management; Projects - Commercial; Public-private partnerships (P3); Renovation

Comment Join the Conversation:

Sign in to our community to add your comments.


Advertisements
 
Tarps manufacturing, Inc.

 
KTA-Tator, Inc. - Corporate Office

 
SAFE Systems, Inc.

 
WEFTEC Show

 
DeFelsko Corporation

 
Sauereisen, Inc.

 
 
 

Technology Publishing Co., 1501 Reedsdale Street, Suite 2008, Pittsburgh, PA 15233

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy Policy   |   Terms & Conditions   |   Support   |   Site Map   |   Search   |   Contact Us