Report: Construction Disputes Dragged On in 2017

Friday, July 20, 2018

Comment | More

Global design and consultancy firm Arcadis (Highlands Ranch, Colorado) recently released a report detailing that while the value of construction disputes in North America dropped for the fourth year in a row, the average time taken to resolve these disputes increased in 2017, surpassing the global average.

The report focuses the causes, duration and value of construction disputes while also looking at how such disputes are handled.

© iStock.com / kirisa99

Global design and consultancy firm Arcadis (Highlands Ranch, Colorado) recently released a report detailing that while the value of construction disputes in North America dropped for the fourth year in a row, the average time taken to resolve these disputes increased in 2017, surpassing the global average.

"In an environment of labor shortages and increased pressure from expediting projects, it is often instinctual to focus on getting a project started first and dealing with consequences later,” said Roy Cooper, head of contractor solutions, North America, for Arcadis.

"Even though many owners are fully aware that taking the time to administer a sound contract and negotiating clauses and terms are best practices, the results still show that failure to do so is an industry-wide problem. This emphasizes the importance of understanding the human factors that play into disputes as much, or even better than, understanding the technical issues themselves. We further explore the common causes of disputes and the related solutions to aid in the future delivery of projects and hope this will serve as a helpful guide for the future."

Report Highlights

For this report, “dispute” was defined as a situation in which two parties typically differ in the assertion of a contractual right, resulting in a decision being given under the contract, which in turn becomes a “formal dispute.”

The value of a dispute is defined as the additional entitlement to that included in the contract, for the additional work or event which is being claimed. The length of a dispute is the period between when it becomes formalized under the contract and the time of settlement, or the conclusion, of the hearing.

In 2017, the average dispute value in North America was $19 million, down from 2016 ($21 million) and less than the global average ($43.4 million). The Middle East had the highest average at $91 million (all values were represented in U.S. dollars), the United Kingdom rang in second with $34 million and continental Europe averaged $29.5 million.

While North America was the lowest in dispute value, it ranked second-highest in average length of disputes (17.7 months), far exceeding the global average (14.8 months).

Continental Europe had the longest average duration, at 18.1 months, followed by the Middle East at 13.5 and the U.K. at 10. The report noted that analysts had anticipated both dispute values and dispute lengths to decrease for North America, yet the dispute length increased from 15.6 months in 2016.

Arcadis

In 2017, the average dispute value in North America was $19 million, down from 2016 ($21 million) and less than the global average ($43.4 million). The Middle East had the highest average at $91 million (all values were represented in U.S. dollars), the United Kingdom rang in second with $34 million and Continental Europe averaged $29.5 million.

“While design errors & omissions continue to be the genesis of many construction claims, the most basic function of poor and/or untimely communication continues to bedevil projects,” said Brian K. Stewart, Esq., Partner, Collins Collins Muir + Steward, LLP.

“In many instances when the problem starts as a technical issue, it can be exacerbated by failing to tackle the issue head on and instead many project members can take an ‘ostrich’ approach, which only causes the situation to fester. The ‘ostrich’ approach is absolutely the wrong way to deal with a developing problem on a project.”

The top three causes of contract disputes globally, which remained the same year over year, include:

  1. Failure to properly administer the contract;
  2. Poorly drafted or incomplete/unsubstantiated claims; and
  3. Employer/contractor/subcontractor failing to understand and/or comply with its contractual obligations.

The most popular methods to resolve the disputes include:

  1. Party-to-party negotiation;
  2. Mediation; and
  3. Arbitration.

The report also noted that contract and specification reviews were considered the most effective claims avoidance technique.

In the North America analysis, the report closes by noting the anticipated increase in large construction projects in 2018.

“With these larger and more complicated projects comes a need to embrace more sophisticated claims-avoidance techniques,” the report says, including:

  • Identifying potential problem areas during the design stage;
  • Encouraging relationship building between the project participants early in the project’s life cycle;
  • Using the most sophisticated technology and techniques the industry can offer to avoid disputes; and
  • Creating a platform where potential project issues can be regularly addressed.

   

Tagged categories: Business matters; Contracts; Disputes; Laws and litigation

Comment Join the Conversation:

Sign in to our community to add your comments.

Advertisements
 
Tarps manufacturing, Inc.
 
QUALITY MADE IN AMERICA —Available near you!
 
CLICK to get a behind-the-scenes look at how Tarps Manufacturing makes the highest-quality tarps right here in the USA — available nationwide.
 

 
Novatek Corporation
 
Dustless Coatings Removal
 
Novatek Corporation, Dustless Coatings Removal Strip, clean and profile all dust free! Comply with new lead standards. Contact today: (866) 563-7800 www.Novatekco.com
 

 
SABRE Autonomous Solutions
 
Imagine being able to remove the operator from the blasting environment
 
This significantly reduces workers exposure to hazards like toxic dust, noise, and repetitive motion injuries.
 

 
Industrial Vacuum Equipment Corp.
 
Hurricane Vacuums
& Dust Collectors
 
Vacuum and dust collector hose, filters and related accessories.
IndustrialVacuum.com
 

 
HoldTight Solutions Inc.
 
Clean surfaces simply don’t rust, and no other product cleans like HoldTight®102.
 
HoldTight®102 is a wet blasting additive that decreases the water’s surface tension, allowing it to get into the profile of the surface and remove ALL contamination, including salts, acids, abrasives, light oils, and greases. HoldTight®102 leaves behind no film and evaporates with the water, providing a surface that is thoroughly clean and ready for coating, rust-free for up to 72 hours.
 

 
Absolute Equipment/Grand Rental Station
 
TIER 4 EQUIPMENT
 
We have Tier 4 Equipment including Air Compressors & Generators for Sale & Rent! Your job may now require Tier-4. www.absoluteequip.com or Call 412-931-6655.
 

 
Graco Inc.
 
Graco EcoQuip 2: Experience the Difference
 
While others claim their equipment is the same, none of them compare to Graco’s EcoQuip 2™ Vapor Abrasive® blasting line. Visit graco.com/ecoquip to learn more.
 

 
RCG America
 
www.glassOx.com
 
Recycled crushed glass factory direct. Pallet to truckloads. Experience quality. Demand savings. Serving PA, MD, DE, NJ, NY, CT, RI, MA, MI, OH, IN, WV, KY.
 

 
ABKaelin, LLC
 
ABKAELIN EH&S SERVICES
 
Programs/Training/Monitoring for Silica, Lead, Noise, Beryllium, Hexavalent Chromium, Cadmium, Hazardous Waste*PM10 & TSP-Lead Ambient Air Monitoring*SSPC C3/C5
 

 
Sauereisen, Inc.
 
Corrosion Resistant Materials for the Wastewater Industry
 
33+ years of successful installations

sauereisen.com
 

 
 
 

Technology Publishing Co., 1501 Reedsdale Street, Suite 2008, Pittsburgh, PA 15233

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

Durability + Design PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy Policy   |   Terms & Conditions   |   Support   |   Site Map   |   Search   |   Contact Us