Iraqi Dam Threatens Failure, Flood

Monday, February 8, 2016

Comment | More

Italian construction firm Trevi Group has secured the contract to make critical repairs to a failing hydroelectric dam in Mosul, Iraq.

The country's largest dam, which had been taken over by the Islamic State (IS) briefly in 2014, faces catastrophic failure from two faults: a “lapse in maintenance” and flawed construction, which sited the structure on unstable soils that erode when in contact with water, The Guardian reported Tuesday (Feb. 2),

By U.S. Army Corps of Engineers / Public domain via Wikimedia Commons
By U.S. Army Corps of Engineers / Public domain via Wikimedia Commons

A “lapse in maintenance” and flawed construction threaten the structural integrity of Iraq's Mosul dam. Trevi Group has won the bid to begin repair and maintenance on the structure.

The poor structural integrity is significant enough that the U.S. military prepared a contingency plan in case of failure, according to Reuters reports.

As far back as 2007, the U.S. ambassador to Iraq and the top American military commander in the country warned that, at worst, “an instantaneous failure of Mosul dam filled to its maximum operating level could result in a flood wave 66 feet deep at the city of Mosul,” Iraq’s second-largest city, about 25 miles away, The Guardian wrote.

Dangerous Territory

At the Rome press conference announcing the bid award, held with U.S. Secretary of State John Kerry, Foreign Minister Paolo Gentiloni confirmed that the Iraqi cabinet and the country’s ministry of water resources had selected Trevi to carry out the rehabilitation and maintenance work.  

Terms of the contract, which reports say will be finalized within a matter of days, were not disclosed.

However, because the dam is located near IS-held Mosul, Italian military will be required to defend the site and protect workers. Prime Minister Matteo Renzi had earlier indicated that 450 troops would be deployed for this purpose, Reuters reported.

"We have been in contact with Baghdad for many weeks, and the Italian forces will be deployed to defend the work site in agreement with the coalition," Gentiloni said during the press conference.

USACE / Public Domain via Wikimedia
By U.S. Army Corps of Engineers / Public domain via Wikimedia Commons

At worst, “an instantaneous failure of Mosul dam filled to its maximum operating level could result in a flood wave 66 feet deep at the city of Mosul,” accordign to a 2007 report.

According to the U.S. Army Corps of Engineers: "in terms of internal erosion potential of the foundation, Mosul dam is the most dangerous dam in the world," ABC Online reported.

Preventing Failure

The Iraqi government has had to address construction flaws in the 2.2-mile-long dam since its completion in 1984, The Guardian wrote. Workers injected a mortar-like grout into the subsoil and cavities to help shore up the foundation and control seepage.

However, the problem grew when Isis seized the dam for a two-week period in 2014. With maintenance disregarded, the structure became further weakened.

Grouting work is underway once again in a long tunnel that stretches under the dam, ABC Online said. Hussein Hamad Ahmed, an engineer at the dam, told the news agency that workers drill down from the tunnel to a specific point, the inject grout to fill any gaps that have appeared underneath.

"Maintenance work is going on 24 hours [a day]," said Riyadh Ezzedine al-Nuaimi, the dam's manager. Three shifts a day keep the work flowing.

Additionally, the U.S. has put sensors on the dam to measure how much it is moving or deteriorating over time, Lt. Gen. Sean MacFarland, the commander of the military operation against Isis, told The Guardian.

If a collapse happens, "it's going to go fast," he told ABC Online.

Trevi’s repair and maintenance of the dam is expected to take 18 months to complete.

   

Tagged categories: Asia Pacific; EMEA (Europe, Middle East and Africa); Infrastructure; Latin America; Locks and dams; North America; Power; Power Plants; Quality Control

Comment Join the Conversation:

Sign in to our community to add your comments.


Advertisements
 
KTA-Tator, Inc. - Corporate Office

 
SAFE Systems, Inc.

 
ABKaelin, LLC

 
HoldTight Solutions Inc.

 
DeFelsko Corporation

 
Tarps manufacturing, Inc.

 
AWWA (American Water Works Association)

 
RCG America

 
Mitsubishi Gas Chemical America

 
Modern Safety Techniques

 
 
 

Technology Publishing Co., 1501 Reedsdale Street, Suite 2008, Pittsburgh, PA 15233

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy Policy   |   Terms & Conditions   |   Support   |   Site Map   |   Search   |   Contact Us