PaintSquare.com
Follow us on Twitter Follow us on LinkedIn Like us on Facebook Follow us on Instagram Visit the TPC Store
Search the site

 

Advertisement

PaintSquare


Coatings Industry News

Main News Page


Seattle Dig Delayed Again

Wednesday, October 28, 2015

Comment | More

The dig on the Alaskan Way Viaduct replacement project underneath Seattle remains in limbo even as repairs continue on the site’s tunnel boring machine, nicknamed Bertha.

Reassembly of the idled machine is taking longer than expected, leading contractor Seattle Tunnel Partners (STP) to push back its restart date by one month. According to a revised STP timeline posted by the Washington State Department of Transportation (WSDOT) last week, Bertha will not resume tunneling until Dec. 23.

WSDOT
Photos: Washington State Department of Transportation

WSDOT announced that the start date to resume boring on the Highway 99 tunnel project has been pushed back until Dec. 23.

The replacement project focuses on the 2-mile-long elevated double-deck road originally built in the 1950s. Damage from a 6.8 magnitude earthquake in 2001 led to the need to stabilize and repair the structure and restrict heavy vehicle traffic.

The 57-foot-diameter tunneling machine, built by Hitachi Zosen, overheated in December 2013, putting a stop to the tunneling. Seals were reported to have failed around the main bearing.

The unit was returned to the pit in August, after repairs were made to the cutter head and additional components were repaired or corrected, while welding and reconnecting of hoses, wires and cables were expected to wrap up after a few months.

This timeline revision puts the Highway 99 tunnel project a little more than two years over the planned completion date of December 2015. With tunneling now projected to be complete in January 2017, the $1.35 billion tunnel is scheduled to open in April 2018, according to WSDOT’s project update.

Maintaining Precision

The adjustment to the schedule will help to ensure that crews get the time they need to successfully complete the repairs, WSDOT says.

Crews were working around the clock on the reassembly of the $80 million machine, the Seattle Times reported Oct. 14, including reconnecting hoses, wires, cables and welding shield pieces and reinforcement plates before testing the moving parts.   

However, STP’s project manager, Chris Dixon, indicated that in the process of gauging placement, the crew is having difficulty maintaining the exact spacing of 14 to 18 mm needed between the rotating parts and fixed parts of the 4-million-pound front end, the Seattle Times reported Oct. 22.

“The movement of these gaps has been a real critical activity,” he said. “We’ve welded it in other places, and switched jacks around, to monitor these gaps.”

Crews working on reassembling the machine are experiencing difficulty maintaining the precise spacing between the rotating and fixed parts on the drilling unit.

Open air testing of the machine was scheduled to occur the week of Oct. 12, but that has not been able to happen yet.

Delivering the News

State tunnel officials presented the timeline to the state legislature’s Joint Transportation Committee on Oct. 22, the Times reported, adding that the team accepted the news “with a congenial attitude.”

However, the committee still sought to understand how the state had paid STP $1 billion of its contract when it has only drilled 11 percent of the tunnel.

Todd Trepanier, WSDOT’s Highway 99 administrator, assured the committee that STP is only paid for the work it has completed. “Even though the tunnel is stopped, they only have $300 million worth of work to do,” he said.

According to Trepanier, much of the work is nearly completed, including the north and south portals, the arched concrete segments that will form the tunnel walls, and the road decks on the Sodo side.

Getting the Ground Ready

In the meantime, STP began injecting grout (a mixture of cement and water) into the soil near Bertha to prepare the ground for the drilling to begin, the Times said in its Oct 14 report.

The process of “jet grouting” is required in Seattle tunnel projects, according to the paper, to control wet soil and assist in accurate drilling. However, for Bertha it serves an additional purpose—stabilizing the ground above the tunnel as the machine exits the pit.

WSDOT Tunnel pieces

According to WSDOT, much of the work is nearly completed, including the north and south portals, the arched concrete segments that will form the tunnel walls, and road decks.

When Bertha leaves the ring-shaped repair vault and heads north, the west and east edges of the cutter would reach dirt while the north and south edges would still grind the curved wall of the concrete pilings.

According to WSDOT spokesperson Laura Newborn, the addition of grout along the ring makes sure the entire cutter head will scrape along a uniformly hard surface.

A WSDOT project update explained that the process would take up to six weeks. Crews will use a high-pressure pump to inject grout into the ground adjacent to the access pit’s north wall, creating a set of interlocking columns approximately five feet in diameter. The top of the columns will begin approximately 20 feet below the surface, and will extend down approximately 40 feet, stopping just above the tunnel route.

Legal Activity

As reported earlier, insurance companies had become involved in a battle over Bertha’s repairs. They do not want to pay the $143 million in anticipated repair costs of a machine that cost $80 million to build. They claim that the design of machine was flawed.

Because of the short distance Bertha had covered in service, consensus held that Hitachi Zosen, the machine’s manufacturer, would be held liable for the repairs. If it had tunneled a little farther, the state or STP would be responsible for repairs.

Meanwhile, according to Puget Sound Business Journal, STP holds WSDOT responsible for the breakdown, having failed to tell it about an eight-inch pipe casing that ultimately led to the damage.

WSDOT Hwy 99 concept

Citing a primary interest in keeping work moving on the tunnel project, WSDOT indicated it will ask for a stay in its recently filed lawsuit and asks STP to do the same, meaning work will be completed before any litigation takes place.

On Oct. 9, WSDOT issued a statement indicating they had filed suit against STP in King County Superior Court.

The filing was prompted by the recent court filings by STP and its insurance companies and was a step to ensure WSDOT will have a right to make legal claims in the future. This lawsuit does not prevent STP from pursuing claims under the terms of the design-build contract, WSDOT stated.

The transportation department said it intends to ask for a stay of its lawsuit until the project is completed and asked STP to join in this request. This delay in the lawsuit will allow for work on the SR 99 Tunnel Project to be completed before litigation takes place. 

Reports indicate that the state has already sustained more than $3 million in overruns and expects another $75 million due to the stoppage.

   

Tagged categories: Concrete; Infrastructure; Laws and litigation; Roads/Highways; Tunnel

Comment Join the Conversation:

Sign in to our community to add your comments.

Advertisements
 
Fischer Technology Inc.
 
DUALSCOPE®FMP100 with DataCenter IP
 
Transfer customized inspection plans from PC to FMP100 using step-by-step guidance with prompts and pictures throughout the measurement procedure
 

 
HoldTight Solutions Inc.
 
Clean surfaces simply don’t rust, and no other product cleans like HoldTight®102.
 
HoldTight®102 is a wet blasting additive that decreases the water’s surface tension, allowing it to get into the profile of the surface and remove ALL contamination, including salts, acids, abrasives, light oils, and greases. HoldTight®102 leaves behind no film and evaporates with the water, providing a surface that is thoroughly clean and ready for coating, rust-free for up to 72 hours.
 

 
KTA-Tator, Inc. - Corporate Office
 
KTA-Tator Training Course Opportunities
 
• IACET Authorized Continuing Education Unit (CEU) Provider
• Live Basic Coatings Inspection Courses
• Customized/Private Courses
• Online/self-paced curriculums
Contact: Tiffany Kelly at 412-788-1300 x217
 

 
DeFelsko Corporation
 
PosiTector SST Soluble Salt Tester
 
Measures the concentration of soluble salts on metal surfaces. Use with all Bresle patch types including the reusable, adhesive-free PosiPatch.
 

 
BASF
 
New resins from BASF will have metals loving water!
 
Excellent corrosion resistance, low VOC, high gloss, thin films www.basf.us/industrialcoatings dpsolutions@basf.com 800-231-7868
 

 
Tarps manufacturing, Inc.
 
QUALITY MADE IN AMERICA —Available near you!
 
CLICK to get a behind-the-scenes look at how Tarps Manufacturing makes the highest-quality tarps right here in the USA — available nationwide.
 

 
Novatek Corporation
 
Dustless Coatings Removal
 
Novatek Corporation, Dustless Coatings Removal Strip, clean and profile all dust free! Comply with new lead standards. Contact today: (866) 563-7800 www.Novatekco.com
 

 
Blastox/The TDJ Group, Inc.
 
Blastox® - One Step Lead Abatement
 
Sandblast additive delivered to jobsite pre-blended to eliminate hazardous abrasive wastes. Why mix, meter or apply at the job-site? Blast with ease and
Let your painters paint!
1(800)-252-7869
 

 
SAFE Systems, Inc.
 
Portable Blast &
Recovery Equipment
 
Trailer or skid mounted blast and recovery equipment. Systems designed for maximum versatility, environmental compliance
and overall cost savings.
Call 1-800-634-7278
 

 
 
 

Technology Publishing Co., 1501 Reedsdale Street, Suite 2008, Pittsburgh, PA 15233

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

Durability + Design PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy Policy   |   Terms & Conditions   |   Support   |   Site Map   |   Search   |   Contact Us