I sat through a pre-construction meeting via conference call today to go over the ins and outs of our upcoming flooring installation. This project will be a combination of a renovated facility, with a new addition being constructed.
We have a scope within each section, installing two dance floors in the renovated side and installing 5,000 square feet of gym flooring in the new construction.
After we were asked to review our approximate duration on-site to complete our work, we were addressed with the question: "How long after the slab pour can you be installing your floor? Is two weeks enough?"
.jpg) |
TuiPhotoengineer / Getty Images |
After we were asked to review our approximate duration on-site to complete our work, we were addressed with the question: "How long after the slab pour can you be installing your floor? Is two weeks enough?"
|
At first, I thought I didn't hear the general contractor right, so I didn't put much emphasis on it. But then it was posed again. The project was behind schedule, they still wanted to be completed in May and they wanted to know how soon after the slab was poured could we be in there installing the floor.
First, let me just say that we are supposed to utilize an on-slab vapor barrier as part of our synthetic gym flooring system that allows us to install up to 100 percent relative humidity in the concrete slab. But, but, but ... two weeks after the pour? Were we really being asked that? We're going to be putting a non-breathing system on essentially a brand-new slab and then expect it to behave in a predictable manner?
Second, how legitimate is this actual request? All other trade work needs to be done before the flooring actually goes in. Not only does that include the HVAC system, lighting and basketball hoops, among others, but they'll all be done within those two weeks?
For the record, our flooring installation instructions ask that "the concrete subfloor will be cured for a minimum of at least 60 days.” That would put us well beyond the proposed opening date for the school. Fortunately, we can offer a two-part epoxy moisture mitigation system, which can be utilized with the only parameters being “newly prepared concrete must be cured for seven days.”
We addressed our timelines and concerns and wrapped up our conference call after the owner stated his position to the general contractor on the importance of the schedule being met. He stated that our call should have been held months ago to state that the flooring couldn't go in during such a short window after placement. But was it really necessary to tell them this months ago? Is it not common knowledge what a typical new construction duration is?
 |
Drazen_ / Getty Images |
For the record, our flooring's installation instructions ask that "the concrete subfloor will be cured for a minimum of at least 60 days.” That would put us well beyond the proposed opening date for the school. Fortunately, we can offer a two-part epoxy moisture mitigation system, which can be utilized with the only parameters being “newly prepared concrete must be cured for seven days.”
|
A few minutes after we wrapped the conference call, my contact with the general contractor called me up to talk one-on-one and address the scheduling concerns that are now a hot-button issue.
A laundry list of items has delayed this project from the start, anywhere from eight days of unanticipated rock removal being undertaken to unforeseen trenchwork that was required with just more piled on top of that. All of these circumstances pushed the start of the project, but not the completion date of the schedule. Do you know who feels the biggest effect of these time crunches? The finishes guy. Us. And this isn't an exception. This has become the norm.
In one of my latest posts, I asked: “Is All of Construction on a Fast-Track?” where I stated “overall project construction schedules and durations have been shortened for years now” and this project we're facing is a perfect example of that.
But what about certain normal expectations? Like the proper curing time for a concrete slab? Or ample time for other trade work to complete their tasks? Is all this out the window for the sake of the grand opening and ribbon cutting?
I'm thankful that we had this conversation in advance so that we could all be on the same page now. However, I'm still shocked that this conversation had to occur. We just took what was a seven-month schedule and are now being forced with looking at four months to complete it all.
After all, we're all problem solvers in construction, right?
About the Author
Eric Lussier is an indoor sports flooring trusted advisor, distributor and subcontractor for 12 years, now working with Precision Athletic Surfaces, based out of Vermont.
He is active in the Construction Specifications Institute (CSI), and is currently president of the Vermont Chapter. Lussier is a construction industry blogger whose work is featured on Let’s Fix Construction, which he co-founded with Cherise Lakeside.
Cherise and Eric recently launched the Let's Fix Construction podcast, which can be found on several platforms or on their website. You can find Eric on Twitter @EricDLussier and on LinkedIn.
|
|
ABOUT THE THE BLOGGER |
Letsfixconstruction.com |
Let's Fix Construction is written by a collective group of construction professionals involved in letsfixconstruction.com, an online impartial platform to provide forward-thinking solutions to many longstanding issues that have plagued construction. Organizers and contributors seek to better the industry by sharing knowledge, while creating open and positive communication and collaboration. Many of the posts have appeared first on letsfixconstruction.com and are republished on Durability + Design with permission. Author information is available at the bottom of each blog entry. |
SEE ALL CONTENT FROM THIS CONTRIBUTOR
|
|
Tagged categories:
Architects;
Business management;
Construction;
Consultants;
Contractors;
Design;
Designers;
Developers;
Engineers;
Good Technical Practice;
Specifiers;
Asia Pacific;
Commercial Construction;
EMEA (Europe, Middle East and Africa);
Flooring system;
Latin America;
North America;
Specification
Comment from Simon Hope, (3/8/2019, 3:55 AM)
|
I feel for you, as always the guys doing the final finishing jobs are pushed beyond the limits by buffoons who come from financial or planning backgrounds without a spark of technical knowledge or understanding. I have had planners just stack all the operations of a two week project into 2 days and proudly turn round and say ' there you go, it can be done, you just need a few more men', what the blithering idiot could not grasp however clearly it was explained was that the operations had to be done consecutively rather than concurrently. You have my sympathy, it is very hard to mitigate for total stupidity!!
|
|
Comment from Stephen Dobrosielski, (3/8/2019, 10:18 AM)
|
It takes 9 months to have a baby, regardless of the number of mothers you put on the job.
|
|
Comment from Michael Halliwell, (3/8/2019, 11:41 AM)
|
Different field, but I can sympathize. I get a lot of calls with totally unrealistic timelines because the "environmental stuff" remains an afterthought. The banks and developers know our timelines and because things like Phase I ESA rely on external information, they take time....but we still get the "but we can get it for next Tuesday, right?" calls :(
|
|
Comment from Joe Chesterfield, (3/13/2019, 6:37 PM)
|
I believe colloidal silicate hydrogels have been successfully used to immobilize moisture in green concrete, allowing for early installation of floor coverings.
|
|
Comment from mark vanner, (1/12/2021, 10:01 AM)
|
Do people not understand that if you pressure and rush the trades than shortcuts are the only option and that is not a good and proper finish to any job :(
|
|
Comment from Hailey Roberts, (3/29/2021, 7:28 AM)
|
I think that soil is also essential when building infrastructure with concrete.
|
|
|