During newbuilding, do I have to stripe coat edges if I am using an edge retention primer?

More items for Coating Application


Selected Answers

From FRIDAY OWAJI of DELATTRE BEZONS on September 7, 2013:
Yes stripe coating the edge is the best thing, but the applicator should determine if the spec calls for it.

From Empty Jasson of Hai Phong on February 22, 2013:
     Yes, during newbuilding, stripe coat must be carried out on all edges.

From James Albertoni of CA Department of Water Resources on January 22, 2013:
     Technically, you only have to do what the spec says. If your spec doesn't call for stripe coating, then it is not required. However, it is always a good idea and will prolong the life of the coating.

From Per Gabrielsson of Free Lance Consultations and Inspections on January 22, 2013:
     Yes, of course. Physical forces drive the coating away from edges. Always stripe coat with brush, if possible. Stripe also a few cm's from edges.

From Tom Schwerdt of Texas Department of Transportation on January 24, 2013:
     Best practices would be to stripe-coat the edges. I have seen numerous "edge retentive" primers which had 50% or less thickness at an edge when compared to the flat.

From Atanas Cholakov of Insignia JFZ on January 23, 2013:
     Per, if this is not highlighted in the coating spec, then RFI needs to be risen to seek clarification. Stripe coat is almost always necessary, but IOZ systems might be exempted. The coating spec insists (rules)... nobody else.

From Atanas Cholakov of Insignia JFZ on January 21, 2013:
     This question can be best answered from your Coating Spec., pre-job meeting. Assessment of structure complexity and accessibility for spray will be an important step with following highlight on areas to be stripe-coated. The paint supplier's tech. rep's opinion is of importance as well.

From Daniel Liu of APC on February 6, 2013:
     Before the project starts, the application procedure, of course including stripe coating, is normally  fixed, mainly based on the specs, during the pre-job conference. If this point is not required or highlighted in the specs, you can apply the stripe coat where necessary, such as poor manual welds with undercuts, etc. In this case, trust your experience!

From Per Gabrielsson of Free Lance Consultations and Inspections on January 23, 2013:
     Atanas, accessibility for spraying has nothing to do with the need for stripe coating. If you aim to spray an edge, how much paint do you actually have on that? And how much dry spraying of adjacent areas? In shipping we know the limitations of the paint supplier;  this is why WE (the owner's inspectors) have to insist in stripe coatings.

Please sign in to submit your answer this question    

Tagged categories: Edge-retentive Primers; Edges


Current PSF Question | Submit a PSF Question | Full PSF Archive

Advertisements
 
SEMicro Division, M.E. Taylor Engineering, Inc.
 
Coatings Adhesion Testers
 
The PATTI® accurately measures the bond strength between coating & substrate. Outfitted properly, the surface can be rough, porous, or curved & >10K psi strong!
 

 
Industrial Vacuum Equipment Corp.
 
Hurricane Vacuums
& Dust Collectors
 
Vacuum and dust collector hose, filters and related accessories.
IndustrialVacuum.com
 

 
SABRE Autonomous Solutions
 
Repeatability
 
The ALPHA1 provides reliable results consistently allowing you to cost your next job with confidence.
 

 
Waterjet Technology Association (WJTA)
 
Click to register today!
 
See the latest automated and handheld UHP waterblasting tools/systems/products. Exhibits, live demos, educational sessions, waterjet short course, networking.
 

 
Vector Technologies Ltd.
 
The Original Performance Proven Vacuum Solutions
 
VecLoader® 616 Double Dump, Continuous Vacuum, 170 HP w/ 2,400 CFM & 28” Hg. 33% More Efficient than traditional vacuum systems! Choose Vector for the most powerful and the most reliable trailer mounted vacuums in the industry! Email us at: inquiry@vector-vacuums.com or call us at: 800-832-4010
 

 
RBW Enterprises, Inc.
 
Robotic Blasting and Painting
 
When using the FasterBlaster and FasterPainter, blasting and painting can be conducted simultaneously. View the video for a full explanation of the operation.
 

 
Abrasives Inc.
 
Discover the MAGIC.
 
Black Magic® coal slag. It’s consistent, cleaner, cuts better, less dust. Get it where you need it, when you need it. Abrasives Inc. info@abrasivesinc.com
 

 
Strategic Materials Inc.
 
Crushed Glass Abrasives
 
TruAbrasives™, a clean crushed glass abrasive superior to other abrasives for performance, health, and environmental benefits.
 

 
WEFTEC Show
 
WEFTEC® 2017. Register Today.
 
WEFTEC® 2017 – Celebrating 90 years in its birthplace, Chicago, is THE event for water professionals, industry experts, and innovators from around the world.
 

 
Axxiom Manufacturing
 
Schmidt Introduces
the New miniBRS
 
Reduced in size, it is incredibly easy to maneuver and operate! The perfect alternative to larger blast & recovery units when project space is limited.
Call 1-800-231-2085
 

 
 
 

Technology Publishing Co., 1501 Reedsdale Street, Suite 2008, Pittsburgh, PA 15233

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

Durability + Design PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy policy   |   Terms & conditions   |   Site Map   |   Search   |   Contact Us