During newbuilding, do I have to stripe coat edges if I am using an edge retention primer?



More items for Coating Application


Selected Answers

From FRIDAY OWAJI of DELATTRE BEZONS on September 7, 2013:
Yes stripe coating the edge is the best thing, but the applicator should determine if the spec calls for it.

From Empty Jasson of Hai Phong on February 22, 2013:
     Yes, during newbuilding, stripe coat must be carried out on all edges.

From James Albertoni of CA Department of Water Resources on January 22, 2013:
     Technically, you only have to do what the spec says. If your spec doesn't call for stripe coating, then it is not required. However, it is always a good idea and will prolong the life of the coating.

From Per Gabrielsson of Free Lance Consultations and Inspections on January 22, 2013:
     Yes, of course. Physical forces drive the coating away from edges. Always stripe coat with brush, if possible. Stripe also a few cm's from edges.

From Tom Schwerdt of Texas Department of Transportation on January 24, 2013:
     Best practices would be to stripe-coat the edges. I have seen numerous "edge retentive" primers which had 50% or less thickness at an edge when compared to the flat.

From Atanas Cholakov of ACT on January 23, 2013:
     Per, if this is not highlighted in the coating spec, then RFI needs to be risen to seek clarification. Stripe coat is almost always necessary, but IOZ systems might be exempted. The coating spec insists (rules)... nobody else.

From Atanas Cholakov of ACT on January 21, 2013:
     This question can be best answered from your Coating Spec., pre-job meeting. Assessment of structure complexity and accessibility for spray will be an important step with following highlight on areas to be stripe-coated. The paint supplier's tech. rep's opinion is of importance as well.

From Daniel Liu of APC on February 6, 2013:
     Before the project starts, the application procedure, of course including stripe coating, is normally  fixed, mainly based on the specs, during the pre-job conference. If this point is not required or highlighted in the specs, you can apply the stripe coat where necessary, such as poor manual welds with undercuts, etc. In this case, trust your experience!

From Per Gabrielsson of Free Lance Consultations and Inspections on January 23, 2013:
     Atanas, accessibility for spraying has nothing to do with the need for stripe coating. If you aim to spray an edge, how much paint do you actually have on that? And how much dry spraying of adjacent areas? In shipping we know the limitations of the paint supplier;  this is why WE (the owner's inspectors) have to insist in stripe coatings.

Please sign in to submit your answer this question    

Tagged categories: Edge-retentive Primers; Edges


Current PSF Question | Submit a PSF Question | Full PSF Archive

Mitsubishi Gas Chemical America
Performance Amine 1,3-BAC

A highly reactive cycloaliphatic diamine offering superior performance. Reasonable cost and curing efficacy makes it suitable for all types of epoxy resin applications.


Axxiom Manufacturing
Schmidt Improves Conversion Kits

Schmidt's conversion kits turn out-of-date blast pots into high quality, efficient blasters. Quick, easy to install with step by step instructions.
Call 1-800-231-2085


SSPC: The Society for Protective Coatings
http://www.sspc.org/

Join SSPC and Enhance
Your Career !


Polygon
POLYGON - Temporary Humidity Control

We specialize in innovative climate control solutions for industrial painting, utilizing alternative energy sources and combining desiccants with heating or cooling.


CESCO
USED EQUIPMENT SPECIALS

Jet Edge water blast cabinet 1995 Model 36-100, excellent condition
Sponge Jet 240L feed unit with a recycler unit
Hotsy Trailblazer
Schmidt pot, 6 ton with 4 outlets, TVII valves, 12V line with controls, Halo safety loading feature, 4 factory welded post for jumbo sack rack
Contact us: 888-772-3726
BlastandPaint.com


Novatek Corporation
Dustless Coatings Removal

Strip it, clean it, and profile it,
all dust free! High production
rates and Blast like finishes.
Comply with new lead
standards.


Midsun Specialty Products
Stopaq Corrosion Protection Services by MSP

Stopaq coatings are impenetrable to water, oxygen and bacteria. Save labor costs with simple surface prep and a 30 year guarantee.
Visit: midsunsp.com/stopaq or Call 888-866-8273

 
 
 
Technology Publishing

The Technology Publishing Network

The Journal of Protective Coatings & Linings (JPCL) PaintSquare
Durability + Design Paint BidTracker JPCL Europe

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy policy   |   Terms & conditions   |   Site Map   |   Search   |   Contact Us
 

© Copyright 2000-2014, Technology Publishing / PaintSquare, All rights reserved
2100 Wharton Street, Suite 310, Pittsburgh PA 15203-1951; Tel 1-412-431-8300; Fax 1-412-431-5428; E-mail webmaster@paintsquare.com