During newbuilding, do I have to stripe coat edges if I am using an edge retention primer?

More items for Coating Application


Selected Answers

From FRIDAY OWAJI of DELATTRE BEZONS on September 7, 2013:
Yes stripe coating the edge is the best thing, but the applicator should determine if the spec calls for it.

From Empty Jasson of Hai Phong on February 22, 2013:
     Yes, during newbuilding, stripe coat must be carried out on all edges.

From James Albertoni of CA Department of Water Resources on January 22, 2013:
     Technically, you only have to do what the spec says. If your spec doesn't call for stripe coating, then it is not required. However, it is always a good idea and will prolong the life of the coating.

From Per Gabrielsson of Free Lance Consultations and Inspections on January 22, 2013:
     Yes, of course. Physical forces drive the coating away from edges. Always stripe coat with brush, if possible. Stripe also a few cm's from edges.

From Tom Schwerdt of Texas Department of Transportation on January 24, 2013:
     Best practices would be to stripe-coat the edges. I have seen numerous "edge retentive" primers which had 50% or less thickness at an edge when compared to the flat.

From Atanas Cholakov of Insignia JFZ on January 23, 2013:
     Per, if this is not highlighted in the coating spec, then RFI needs to be risen to seek clarification. Stripe coat is almost always necessary, but IOZ systems might be exempted. The coating spec insists (rules)... nobody else.

From Atanas Cholakov of Insignia JFZ on January 21, 2013:
     This question can be best answered from your Coating Spec., pre-job meeting. Assessment of structure complexity and accessibility for spray will be an important step with following highlight on areas to be stripe-coated. The paint supplier's tech. rep's opinion is of importance as well.

From Daniel Liu of APC on February 6, 2013:
     Before the project starts, the application procedure, of course including stripe coating, is normally  fixed, mainly based on the specs, during the pre-job conference. If this point is not required or highlighted in the specs, you can apply the stripe coat where necessary, such as poor manual welds with undercuts, etc. In this case, trust your experience!

From Per Gabrielsson of Free Lance Consultations and Inspections on January 23, 2013:
     Atanas, accessibility for spraying has nothing to do with the need for stripe coating. If you aim to spray an edge, how much paint do you actually have on that? And how much dry spraying of adjacent areas? In shipping we know the limitations of the paint supplier;  this is why WE (the owner's inspectors) have to insist in stripe coatings.

Please sign in to submit your answer this question    

Tagged categories: Edge-retentive Primers; Edges


Current PSF Question | Submit a PSF Question | Full PSF Archive

Advertisements
 
Detail Masters
 
Overspray Removal
 
We offer professional, turnkey service and unparalleled quality!
Our process can save hundreds— even thousands of dollars. It's fast, environmentally safe and 100% guaranteed.
 

 
SAFE Systems, Inc.
 
Enduroguard -
The Tough Cable
for a Tough Industry.
 
Reduce maintenance costs and down time, increase job site safety with Enduroguard Cable. Available exclusively from SAFE Systems. UL listed, flexible, abrasion resistant and cut resistant.
 

 
Industrial Vacuum Equipment Corp.
 
Hurricane Vacuums
& Dust Collectors
 
Vacuum and dust collector hose, filters and related accessories.
IndustrialVacuum.com
 

 
Novatek Corporation
 
Novatek Corporation, Dustless Coatings Removal
 
Strip, clean and profile all dust free! Comply with new lead standards. Contact today: (866) 563-7800
 

 
Atlantic Design, Inc.
 
BUILDING INNOVATION, NOT IMITATION
 
The smallest version of our Blast Vacuum Recyclers, this ADI 2300CFM 2-Pot is a cleverly designed power package for those smaller jobs. 866.Call.ADI
 

 
HoldTight Solutions Inc.
 
NO FLASH RUST - NO CONTAMINANTS
 
Our HoldTight®102 salt remover & flash rust
preventer prevents flash
rust by removing surface contaminants. Contact us
for your nearest distributor.
(800) 319.8802 sales@holdtight.com
 

 
Advanced Recycling Systems
 
ADVANCED RECYCLING SYSTEMS (ARS)
 
Recycling Machines, Dust Collectors, Rapid Deployment units are time-tested and approved for the rugged industrial environment. Contact ARS today!
(330)536-8210
 

 
Clemco Industries Corp.
 
Maximum Dust Suppression Systems Start at $14,950
 
The system comprises proven technology and equipment with user-friendly flexibility in mind. See it in action.
 

 
DeFelsko Corporation
 
PosiTector SHD Shore Hardness Durometer
 
PosiTector SHD measures the hardness of non-metallic materials. Features a measurement timer, auto ignore mode and internal memory. Shore A or D available.
 

 
Aggreko
 
Portable Heating Rentals
 
Rental heaters are available for your painting/coating project. Aggreko offers stand alone or in-line heaters, ready to rent. 24/7 service, nationwide.
844-433-9802
 

 
 
 

Technology Publishing Co., 2100 Wharton Street, Suite 310, Pittsburgh PA 15203-1951

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

Durability + Design PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy policy   |   Terms & conditions   |   Site Map   |   Search   |   Contact Us