PaintSquare.com
Follow us on Twitter Follow us on LinkedIn Like us on Facebook Follow us on Instagram Visit the TPC Store
Search the site

 

Advertisement

PaintSquare


Coatings Industry News

Main News Page


Agency Wants Out of Botched $120M Hub

Tuesday, April 30, 2013

More items for Environmental Controls

Comment | More

Already $80 million over budget and more than two years behind schedule, a $120 million Maryland transit center will not be used as planned because its structural flaws are too expensive to repair and maintain, the hub's intended operator now says.

And so, as it has previously warned, the Washington Metropolitan Area Transit Authority (WMATA) has told Montgomery County (MD), where the structure is located, that the agency will “not accept the Transit Center as contemplated by the Memorandum of Understanding between WMATA and Montgomery County,” according to a letter Friday (April 26) from the Montgomery County Council to the County Executive.

SSTC - Kiss & Ride
Photos: Montgomery County Government

The center's top level features 54 "Kiss & Ride" spaces and taxi spaces.

The letter quotes a report in the Washington Post that says A. Robert Troup, the transit agency’s deputy general manager of operations, notified county officials in a letter April 12 that the building falls short of standards outlined by the agency in the agreement.

'Inordinate Maintenance Burden'

The issues are of a “magnitude and severity,” Troup said, that even if repaired “would unnecessarily place an inordinate maintenance burden onto WMATA,” the Washington Post reported, quoting the letter.

Construction on the three-story, multimodal Paul S. Sarbanes Silver Spring Transit Center outside Washington, D.C., began in 2008, but concerns arose in 2010 and construction stalled more than a year ago in a dispute over major flaws reported in the concrete.

Under a 2008 agreement, WMATA is supposed to take control of the hub from Montgomery County and operate the center after completion.

Concrete Cracking, Coating Damage

Independent analysts have determined that the concrete falls short of the required 10-inch minimum thickness on two of the center's three levels, county officials have said.

SSTC - escalators

Concerns about cracked concrete, concrete thickness, and other problems arose as early as 2010. Construction began in 2008.

Other issues have included damaged protective coatings on embedded steel, extensive cracking in the slabs, and inadequately strengthened concrete and missing steel supports. At one point during construction, a post-tensioning cable “popped out of the concrete and cracking was observed,” a structural study reports.

The prime contractor, Foulger-Pratt, of Rockville, MD, says that the structure is sound.

Montgomery County Council president Roger Berliner has called the situation a “serious problem.” The county determined earlier this month that only 37 percent of the structure's concrete slab thickness is within the allowable construction tolerances (42 percent is too thick, and 21 percent is too thin, the county says).

Scaling Back

Now, WMATA reportedly says that it will offer only local bus service from the center—and only after repairs are complete. Furthermore, the agency says, it will “no longer pursue plans for inter-city bus operations from the center,” according to The Post.

The letter was reportedly delivered April 12 to David Dise, Montgomery County’s director of the Department of General Services, according to the council. Now, the council wants to know why it was not informed of WMATA’s decision and has asked the county executive to appear before the panel May 1 with an update.

SSTC _ Storm Drain

Final concrete work on the last deep storm drain manhole was on track for completion in late 2011 as part of the on-site stormwater management system.

Repairs are not expected to begin until this summer, and the scope, cost and responsible party remain in hot dispute.

Structural Study: 'Errors and Omissions'

An independent structural evaluation of the superstructure commissioned by the county and released last month concluded that “errors and omissions” by designer Parsons Brinckerhoff, Foulger-Pratt, and inspections and materials testing firm Robert B. Balter Co. had left the center unusable and “a significant safety hazard.”

The 101-page report details numerous design problems, including:

  • Insufficient corrosion inhibitors in concrete;
  • Failure to consider “various required limitations on stress induced during initial post-tensioning”—stresses that induced cracking, the report says; and
  • Induced forces that “overbalanced” the structure due to post-tensioning forces that exceeded the weight of the slabs, beams and girders.

The report says that inspections performed during construction “were not per” the contract requirements and that the concrete used “has lower compressive strength than required” by the contract. The study also noted “insufficient design/construction coordination.”

SSTC

Only 37 percent of the concrete thickness in the structure is within acceptable construction tolerances, according to an independent structural study.

Although the concrete requires that the structure have a 50-year service life, the structural analysis said that corrosion of the concrete slabs where the “epoxy coating is compromised” could begin by 12.5 years.

What Now?

WMATA has not commented publicly on the letter obtained by The Washington Post. It is not clear who would operate the center if WMATA does not, or what legal fallout would ensue should WMATA bail out.

Funded 53 percent by federal funds, 11 percent by Maryland and 36 percent by the county, the hub was supposed to generate “over 4,200 additional daily bus and rail trips” and be the basis of a mixed-use project that would also include apartments, condominiums and a hotel.

SSTC - Downtown Development

The transit center was supposed to anchor an extensive mixed-use development in the Washington, D.C., suburb of Silver Spring, MD. Its future is now highly uncertain.

Dise told the Post that he thought the letter was “an initial position,” not “a final position.”

Montgomery County said also expressed confidence in a statement that said: “The remediated Transit Center will open with the expected 50-year life span with full service at no additional cost to county taxpayers once the prescribed fixes are completed."

County spokesman Patrick Lacefield told The Gazette of Maryland that WMATA's letter was “not serious.”

“There are other options,” Lacefield told the paper, “but we’re not talking about those yet.”

   

Tagged categories: Business management; Concrete; Concrete defects; Concrete repair; Corrosion inhibitors; Design; General contractors; Government contracts; Inspection; Mass transit; Public Transit; Rebar; Structural steel

Comment Join the Conversation:

Sign in to our community to add your comments.

Advertisements
 
Aggreko
 
Dehumidification, Power and Temperature Control Rentals
 
Aggreko offers rental solutions for your painting/coating project. Dehumidifiers, cooling, heating, power and 24/7 service, nationwide.
844-433-9802
 

 
SAFE Systems, Inc.
 
Enduroguard -
The Tough Cable
for a Tough Industry.
 
Reduce maintenance costs and down time, increase job site safety with Enduroguard Cable. Available exclusively from SAFE Systems. UL listed, flexible, abrasion resistant and cut resistant.
 

 
Detail Masters
 
Overspray Removal
 
We offer professional, turnkey service and unparalleled quality!
Our process can save hundreds— even thousands of dollars. It's fast, environmentally safe and 100% guaranteed.
 

 
Strategic Materials Inc.
 
Crushed Glass Abrasives
 
Competitively priced, high-performing crushed glass abrasive. Available today. Toll-free 1-866-775-6226
 

 
BASF
 
New resins from BASF will have metals loving water!
 
Excellent corrosion resistance, low VOC, high gloss, thin films www.basf.us/industrialcoatings dpsolutions@basf.com 800-231-7868
 

 
HoldTight Solutions Inc.
 
NO FLASH RUST - NO CONTAMINANTS
 
Our HoldTight®102 salt remover & flash rust
preventer prevents flash
rust by removing surface contaminants. Contact us
for your nearest distributor.
(800) 319.8802 sales@holdtight.com
 

 
Harsco
 
Find BLACK BEAUTY® Abrasives
 
Use our online tool to search by address, city or zip code to find where you can buy BLACK BEAUTY® abrasives. Or call us toll free: 1-888-733-3646
 

 
Fischer Technology Inc.
 
NEW PROBE FOR MEASURING TSA THICKNESS
 
Paired with the PHASCOPE PMP10, Fischer’s new probe is quick and accurate for measuring thermally sprayed aluminum on stainless steel. Click to learn more.
 

 
Bullard
 
Upgrade with the Bullard GenVX
 
Click here to learn how you can get a GenVX Helmet and Win.
 

 
CHLOR*RID International Inc.
 
SOLUTIONS THAT WORK
 
Companies that invest in corrosion control use CHLOR RID products
  • Soluble salt removal liquid
  • Test kits to verify contamination levels
  • Surface passivation to hold the blast
INFO@CHLOR-RID.COM 800.422.3217
 

 
 
 

Technology Publishing Co., 1501 Reedsdale Street, Suite 2008, Pittsburgh, PA 15233

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

Durability + Design PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy policy   |   Terms & conditions   |   Site Map   |   Search   |   Contact Us