PaintSquare.com


The First Word in Protective & Marine Coatings

A Product of Technology Publishing / PaintSquare
JPCL | PaintSquare News | Durability + Design | Paint BidTracker

Power Plant Coating Systems: Selecting and Sourcing

Paint and Coatings Industry News

Main News Page


Bad Bolts Snag Bay Bridge Work

Tuesday, April 2, 2013

More items for Program/Project Management

Comment | More

Construction on the east span of  California’s new Bay Bridge has hit a snag after workers discovered over 30 broken bolts on the new eastern span, state transportation officials announced.

Heavy-duty bolts, installed for seismic stability, popped loose and damaged the bolts just days after crews tightened started tightening them, the Metropolitan Transportation Commission said. 

In early March, workers started tightening nuts on both ends of 96 bolts, also called anchor rods; a total of 288 rods have been installed on the span. The bolts range from 9 to 24 feet long and are three inches in diameter.

Only a few days later, the crew returned to discover that 32 of the bolts had broken loose.

Bay Bridge construction
Photos: Caltrans Bay Area Toll Authority California Transportation Commission

One-third of anchor rods, or bolts, installed on the easternmost part of the Bay Bridge popped loose just days after crews started tightening them, transportation officials announced.

MTC, which oversees the Bay Bridge project with Caltrans, held a meeting on March 27 to present information on the broken bolts.

Assessing the Problem

Tony Anziano, Caltrans Toll Bridge Program Manager, presented information on the busted bolts.

"This is certainly something that merits briefing," Anziano said, explaining that the large rods connect two columns that rise from the underwater foundation to the concrete pier cap.

In some cases, the rods go entirely through the concrete cap, or are embedded into it, limiting access to rods in the middle portion of the cap.

The rods were tensioned between March 1 and 5; broken rods were discovered between March 8 and 15, Anziano said. Bolts were originally installed in 2008.

"Within a week, we started seeing evidence that these rods were breaking in place. At this point in time, we are still in the process of assessing the situation," said Anziano.

So far, testing has shown that hydrogen has caused the problem, explained Anziano.

seismic retrofitting projects

The bolt in the foreground is lifted about the area that it should be flushed with, giving a "pretty clear indication" that the rod is broken, Caltrans officials explained.

Possible Repairs

Caltrans is still looking into possible solutions, which they expect to develop within a matter of weeks.

"We have actually done a fair amount of laboratory and materials testing. We've taken some of these rods out. They're not easy to get out," Anziano said.

"They actually have to be extracted as far as you can pull them out, then you have to cut a piece off, extract a little bit further, cut a piece off," he said. There are only five feet of clearance to work with, and the rods are at least nine feet long.

According to Anziano, three of the rods have been sent for metallurgical testing and hydrogen was found, which often causes the type of fracture found on the rods.

"Hydrogen is one of those things that works its way in in ways that you don't always typically see. And that's why hydrogen is an issue when you're dealing with steel. Even with the most rigorous inspection practices, hydrogen somewhow sneaks its way in and manifests itself in situations like this," Anziano explained.

While some of the rods can be replaced, an alternate design solution may be implemented where rods cannot be accessed.

Caltrans

A solution and timetable for the fix have not yet been determined, and some of the rods might not be accessible, requiring a second solution for repairs.

'Greater Challenges'

The new Bay Bridge is scheduled to open this Labor Day weekend, and officials remain optimistic that the bolt problem won't delay the opening.

"We have surmounted far greater engineering challenges than this one in getting this bridge constructed, and I have no doubt that we will get through this one as well," Steve Heminger, executive director of MTC, said at the meeting.

Heminger said that they are "certainly mindful" that someone will have to be responsible for the extra cost.

"I think the cost will end up being a rounding error in terms of this project," Heminger told KQED. "We're talking about a $6 billion bridge, and I can't conceive of a solution that's even going to cost a fraction of that amount."

Randy Rentschler with MTC said there are $300 million in contingency funds built into the original budget, and fixing the bolts won't even make a dent in that amount, local CBS affiliate Channel 5 KPIX reported.

The bridge has been under construction for over a decade, and the bolts aren't the first problem.

Sections of the steel deck that were fabricated in China delayed work for months when microscopic cracks were found and further inspections delayed work when the integrity of welds on the piers of the new skyway section were questioned.

And then there were accusations that an inspector faked seismic inspection reports on another, unrelated project.

   

Tagged categories: Bridges; Concrete; Construction; Department of Transportation (DOT); Galvanized steel; Performance testing; Retrofits; Steel

Comment from Donald L Crusan, (4/2/2013, 10:04 AM)

Looks like an extremely poor desin that did not allow for repair and a quickly cobbled together specification for Dyson. Considering this protest: http://www.sfexaminer.com/local/2013/03/bad-bay-bridge-steel-rods-originated-ohio & this banner “Bay Bridge: 100% Foreign Steel”, I wonder if someone at CalTran didn't really substitute the OH bolts with Chinese and sell the American Made Bolts. Great Metallurgy will sniff out the truth.


Comment from peter gibson, (4/2/2013, 11:04 AM)

Materials testing,when the project is well underway !! The ineptness just keeps on going...


Comment from Tom Schwerdt, (4/3/2013, 8:32 AM)

In a large project, ongoing materials testing is not unusual. The contractor isn't going to just assemble all of the materials onsite before beginning construction. Materials tend to arrive onsite regularly throughout a large project.


Comment from M. Halliwell, (4/3/2013, 10:45 AM)

Peter, Tom is quite right. Most suppliers cannot produce enough in one batch to fully supply a bridge or other major project of this magnitude, so on-going testing is used to try to make sure the batches remain consistent. Sure, when it comes to on-going materials testing during construction, most people think of concrete...but steel testing goes on too. It's unfortunate that hydrogen induced fracturing of the rods has occurred, but at least it was caught during construction, not after the bridge was open to traffic or (worse yet) after a catastrophic failure.


Comment from Donald L Crusan, (4/4/2013, 3:36 PM)

I do and have always done a tremendous amount of recieving inspection, sometimes for materials that are new to me. But, by usinf certified material test reports, purchase orders, and inspection test results we get a great handle on what we have recieved. After a few go arounds and Billy Russel can attest, a bogus MTR stands out immediately and raises a red flag.In fact metallurgical testing of steel products is probably more required than concrete or coatings.


Comment Join the Conversation:

Sign in to our community to add your comments.

SAFE Systems, Inc.
Portable Dust Collectors for Tough Environments

Trailer and skid-mounted models in numerous sizes, powered by electric and/or diesel. Sloped roofs, multiple dust inlets, high static, dampered fans. Lockable power & drive compartments.


JPCL Europe
Special EMEA edition!

Now, the publisher of JPCL offers essential news and knowledge for protective and marine coatings professionals in Europe, the Middle East and Africa: www.jpcleurope.com


Safway Services
Suspended Access Made Easy With QuikDeck™

The smart choice for suspended access, QuikDeck’s interchangeable, lightweight components make them easy to set up and reassemble when you need to move.


U.S. Zinc

Offering custom grades and packaging of zinc dust, oxide, metal and fines, U.S. Zinc provides direct shipping to locations worldwide. Helping the world work™


Simpson Strong-Tie
Repair, Protect & Strengthen

Need a coating? Turn to Fox. We have solutions to repair, protect and strengthen concrete, steel and wood substrates. Call 888-760-0369 or email info@foxind.com


Atlantic Design, Inc.
GOING PLACES YOU ONLY DREAM ABOUT!

We custom design.
We sell new & used.
We upgrade.
We retrofit.
We rent.
What are your equipment needs?
Cleverly simple. Clearly ADI. 866.Call.ADI


HoldTight Solutions Inc.
NO FLASH RUST -
NO CONTAMINANTS

Our HoldTight®102 salt remover & flash rush inhibitor prevents flash rust by removing surface contaminants.
Contact us for your nearest distributor. (800) 319.8802 sales@holdtight.com

 
 
 
Technology Publishing

The Technology Publishing Network

The Journal of Protective Coatings & Linings (JPCL) PaintSquare
Durability + Design Paint BidTracker JPCL Europe

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy policy   |   Terms & conditions   |   Site Map   |   Search   |   Contact Us
 

© Copyright 2000-2014, Technology Publishing / PaintSquare, All rights reserved
2100 Wharton Street, Suite 310, Pittsburgh PA 15203-1951; Tel 1-412-431-8300; Fax 1-412-431-5428; E-mail webmaster@paintsquare.com