PaintSquare.com
Follow us on Twitter Follow us on LinkedIn Like us on Facebook Follow us on Instagram
Search the site

 

Download our free e-book! Overcoating bridges and other structures.

Coatings Industry News

Main News Page


Containment Issues Stall Plant Restart

Thursday, February 28, 2013

More items for Health & Safety

Comment | More

Offline for almost two years, a Nebraska nuclear plant was told this week that it must address additional issues before being allowed to restart, according to federal regulators.

The U.S. Nuclear Regulatory Commission issued an updated Confirmatory Action Letter (CAL) on Tuesday (Feb. 26) outlining three additional actions the Omaha Public Power District (OPPD) officials have agreed to take before restarting the Fort Calhoun nuclear plant.

The new CAL items include a requirement to address safety system functional failures, containment internal structure issues, and the use of Teflon as a sealant on electrical cables inside containment.

Photos: Omaha Public Power District

The NRC issued an updated action letter on Feb. 26 with three new requirements for restarting the Fort Calhoun Station nuclear power plant in Omaha.

The plant shut down on April 9, 2011 for a scheduled refueling outage and was nearing completion on June 3, 2011, when flooding required management to suspend outage work and restart activities to focus on flood protection.

Located 19 miles north of Omaha, it is owned and operated by OPPD.

The amount of flooding, which OPPD described as "unprecedented in the U.S. nuclear power industry," peaked at over 1,006 feet above mean sea level and stayed close to that level for more than a month. The plant was protected to 1,014 feet.

Identify and Resolve Issues

NRC previously issued a CAL in June 2012 with a list of action items, or the "Restart Checklist."

The updated CAL, addressed to OPPD's VP and Chief Nuclear Officer, Lou Cortopassi, said the purpose of the Restart Checklist was to verify that the "issues that resulted in the prolonged performance decline at Fort Calhoun Station are resolved."

NRC is requiring OPPD to identify the causes and resolve issues that led to numerous safety system functional failures (SSFF) that were identified over the course of a year. If a key system has the potential to fail, the NRC defines it as a SSFF.

One example of a SSFF at the Fort Calhoun plant was an electrical switchgear fire in June 2011 that disrupted power to vital systems and components needed for the safe shut down of the plant, the NRC said.

OPPD must identify the causes and resolve two existing conditions inside containment. Plant workers discovered that structures supporting equipment did not meet all design requirements. Also, over 600 pipes housing electrical cables that run through the containment building are insulated using a material known to degrade in some accident scenarios involving high radiation exposure.

'Significant Progress'

OPPD acknowledged receipt of the revised CAL in a message on its website that said, "OPPD has been aware of all of the items in the new CAL and has been working on them for months.

"Significant progress has been made with NRC inspections well underway. The NRC inspections and the extensive work will add value to help bring Fort Calhoun back to a high performing plant."

OPPD President and CEO Gary Gates stated, "OPPD leadership and our board of directors are committed to doing everything possible to return Fort Calhoun Station to a high level of performance in a safe, efficient and timely manner."

On Jan. 8, 2013, NRC and OPPD held a public meeting to discuss progress made toward restarting the plant.

OPPD presented its status for each Restart Checklist item and stated that its flood recovery plan was 94 percent complete.

System Discrepancies

In December 2012, OPPD released a slide presentation regarding containment internal structures (CIS). The history and identification of the CIS issues at the plant was provided by Bernie Van Sant, the district's CIS Project Engineering Lead.

An aerial photograph from June 15, 2011, shows the "unprecedented" level of flooding that Fort Calhoun Station withstood for more than a month.

According to the presentation, the issue involves the concrete CIS that supports plant components and systems inside containment.

During an extended power uprate analysis, a discrepancy was discovered with the containment cooling water system pipe supports. Issues were then identified with original CIS calculations that included incorrect, incomplete or missing calculations; inconsistencies between calculations and drawings; and incomplete consideration of all load combinations.

New design options were presented by Tom Dailey, CIS Project Manager. He listed the current preferred option as cast-in-place concrete, explaining that there are fewer interferences compared to the structural steel or precast concrete options.

In the closing remarks, Bruce Rash, the Recovery Director, noted that OPPD was "committed to safe restart" and was "dedicated to support NRC inspection of CIS operability for restart."

About the Plant

Fort Calhoun Station is a 478.6-megawatt nuclear power plant located on the Missouri River. Designed and constructed at an initial cost of $178 million, the platn began producing electricity on Sept. 23, 1973.

The containment building was constructed with steel-reinforced concrete. The walls are almost four feet thick, a one-fourth-inch-thick carbon steel liner ensures leak-tightness, and the floor is more than 12 feet thick, according to OPPD.

In 1993, the NRC granted the station a license extension to 2013; in 2003, NRC again extended the license, this time by 20 years.

   

Tagged categories: Concrete; Nuclear Power Plants; Regulations; Steel

Comment Join the Conversation:

Sign in to our community to add your comments.

Advertisements
 
Clemco Industries Corp.
 
Maximum Dust Suppression Systems Start at $14,950
 
The system comprises proven technology and equipment with user-friendly flexibility in mind. See it in action.
 

 
SEMicro Division, M.E. Taylor Engineering, Inc.
 
Coatings Adhesion Testers
 
The PATTI® accurately measures the bond strength between coating & substrate. Outfitted properly, the surface can be rough, porous, or curved & >10K psi strong!
 

 
SAFE Systems, Inc.
 
Custom blast rooms
by SAFE Systems
 
Don't waste time and money "making do" with a "standard" design. Let us work with you to design and build the system that best fits your requirements.
Call 1-800-634-7278
 

 
SABRE Autonomous Solutions
 
Safety, Productivity, Quality. Robotic Blasting
 
Learn how this simple to use, field deployed, automatic robot is eliminating hazards in major confined, cluttered and complex surface preparation projects.
 

 
Sidewinder/Persyst Enterprises, Inc.
 
The Sidewinder Model M2 Solvent Recycler
 
Combat the rising cost of gunwash, thinners, acetone & more while drastically reducing waste disposal coat.
 

 
BASF
 
New resins from BASF will have metals loving water!
 
Excellent corrosion resistance, low VOC, high gloss, thin films www.basf.us/industrialcoatings dpsolutions@basf.com 800-231-7868
 

 
Corrosion Probe, Inc.
 
From Detection to Correction
 
Corrosion Probe, Inc. has the Most Concrete Coatings Experience and Expertise. Contact us today at
860-767-4402, www.cpiengineering.com
 

 
Blastox/The TDJ Group, Inc.
 
Blastox® - One Step Lead Abatement
 
Sandblast additive delivered to jobsite pre-blended to eliminate hazardous abrasive wastes. Why mix, meter or apply at the job-site? Blast with ease and
Let your painters paint!
1(800)-252-7869
 

 
Bullard
 
The Next Generation
of Blasting
 
• Lightest
• Coolest
• Most Comfortable
• Most Dependable
 

 
Safway Services
 
Your Access Advantage. QUIKDECK®
 
Provides safe, factory-floor-like working conditions. Can be engineered to fit almost any shape, structure or size. Modular platform easily assembled from just a few basic components. Excellent containment. Applications include vessels, offshore rigs and bridges.
 

 
 
 

Technology Publishing Co., 2100 Wharton Street, Suite 310, Pittsburgh PA 15203-1951

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

Durability + Design PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy policy   |   Terms & conditions   |   Site Map   |   Search   |   Contact Us