PaintSquare.com
      | Connect Follow us on Twitter Like us on Facebook
About | Subscribe | Advertise
  

 

Download our free Specialty Function Coating Systems eResource Book

Paint and Coatings Industry News

Main News Page


60-Day Delay to Cost Contractor $60K

Monday, October 3, 2011

More items for Program/Project Management

Comment | More

An Arkansas design-build contractor is facing a $60,000 fine for missing a project deadline by 60 days.

The Delta Regional Airport Authority, near Colt in eastern Arkansas, voted unanimously Thursday night (Sept. 29) to impose a $1,000-a-day fine on Rose Construction Inc., of Covington, TN, for delays in completing grading and drainage work over the summer, the Times-Herald of Forrest City reports.

 Garver Engineers

 Garver Engineers

The new airport will replace two constrained facilities in neighboring counties.

Blake Roberson of Garver Engineers, which is overseeing construction of the $17 million airport, said the 60-day time frame was settled after factoring in time for suspensions of work due to weather and other factors. Roberson told the board that the contract with Rose Construction allowed for a penalty of up to $1,000 per day for each day over the allotted time limit, the Times-Herald reported.

Appeal Possible

Roberson said Rose Construction officials will be invited to the October board meeting if they want to appeal the penalty.

Company officials did not respond Monday to a request for comment. The company performs design-build, construction, maintenance, field and other services for civil-utility, structural, industrial, commercial and special projects.

Plans for the new airport include a 5,003-foot runway; a full parallel taxiway; apron tie-down space for nearly 30 aircraft; T-hangars; a terminal area with space for a general aviation terminal building; fueling facilities; space for corporate, private, and additional T-hangar development; vehicle parking; and an access road. Future planned improvements include a 1,000-foot extension of the runway and taxiway.

‘They Could Have Been Working’

Roberson and DRAA chairman John Kerr said there had been several days when the company could have been working at the Colt site but prioritized other projects for completion, the newspaper reported.

Board member Shannon Hobbs, who works in the Colt area, said he could recall several days early in the process when he felt work could have been taking place, but equipment wasn't moving.

“They came in here heavy and brought all of their equipment and everything,” said Hobbs, according to the newspaper. “It looked like they were going to work, and then all of a sudden, there was nothing going on out at our site.

“It was like John said: They had something else to do and went and took care of that when they could have been working. There were a lot of pretty days they could have been working when there was nothing going on.”

Days Catalogued

Roberson told the board that Garver officials have catalogued the work and progress from the beginning of the contract and said he could provide the board with a list of days when work was not taking place.

Neither Roberson nor board officials could be reached Monday for additional comment.

   

Tagged categories: Airports; Construction; Contracts

Comment Join the Conversation:

Sign in to our community to add your comments.

Armakleen Company, The
ARMEX when nondestructive cleaning is critical

The gentle physical propriety of baking soda but yet aggressive cleaning ability is what makes ARMEX the only choice for nondestructive abrasive blasting.


SAFE Systems, Inc.
Custom blast rooms
by SAFE Systems

Don't waste time and money "making do" with a "standard" design. Let us work with you to design and build the
system that best fits
your requirements.
Call 1-800-634-7278


Chicago Corrosion Group
Vendor-neutral corrosion consulting

What you don’t know about painting is costing you a fortune. Call today to see how CCG’s vendor-neutral, owner’s advocacy saves our clients millions.


CS Unitec
Surface Prep & Material Removal

CS Unitec’s Floor Planers remove coatings & corrosion from concrete & metal surfaces. Produce keyed profiles for waterproofing applications. info@csunitec.com


Armorthane
Corrosion Coatings for Protection and Repair

Buy POLYURETHANE or POLYUREA coatings and spray surfaces for years of proven chemical resistance, water- and weather-proofing, and structural improvements.


CHLOR*RID International Inc.
Free Webinar

Learn about soluble salts, along with a discussion on allowable levels.
More information at
www.chlor-rid.com,

800-422-3217


PreTox Products - NexTec, Inc.
GOT LEAD? Specify Pretox System products

The ONLY Lead Stabilizer Compatible with All Paint Removal Methods. Works with all Blast Media: Grits | Recyclable Abrasives | CO2 | Water | Power Tools | Etc. Call Dave Steffen at 800.338.8296.


Sidewinder/Persyst Enterprises, Inc.
The Sidewinder Model M2 Solvent Recycler

Combat the rising cost of gunwash, thinners, acetone & more while drastically reducing waste disposal coat.


Thermion Inc
Buy Back Program

We are offering $5,000
credit for your old Model
This drive system is
being discontinued by
the manufacturer.
More information at
thermioninc.com
877.884.3428

 
 
 
Technology Publishing

The Technology Publishing Network

The Journal of Protective Coatings & Linings (JPCL) PaintSquare
Durability + Design Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy policy   |   Terms & conditions   |   Site Map   |   Search   |   Contact Us
 

© Copyright 2000-2015, Technology Publishing / PaintSquare, All rights reserved
2100 Wharton Street, Suite 310, Pittsburgh PA 15203-1951; Tel 1-412-431-8300; Fax 1-412-431-5428; E-mail webmaster@paintsquare.com