PaintSquare.com


The First Word in Protective & Marine Coatings

A Product of Technology Publishing / PaintSquare
JPCL | PaintSquare News | Durability + Design | Paint BidTracker

Download our FREE eBook on New Technology Coatings for Corrosion Control

Paint and Coatings Industry News

Main News Page


Chevron Faces $423K Fine for Pipeline Spill

Tuesday, November 2, 2010

Comment | More

Chevron Pipe Line Co.

The federal government has proposed a $423,600 fine against Chevron Pipe Line Co., citing inadequate corrosion control, pipeline protection and other failures for the release of 800 barrels of crude oil near the University of Utah in June.

The civil penalty follows an investigation by the U.S. Pipeline and Hazardous Materials Safety Administration (PHMSA) into the June 12 leak, which dumped 33,600 gallons of crude into Red Butte Creek and Canyon in Salt Lake City.

The leak, which stemmed from a one-inch hole on the top of the pipe, continued for more than 10 hours before Chevron knew of it.

 “As a result of the investigation, it appears that you have committed probable violations of the Pipeline Safety Regulations, Title 49, Code of Federal Regulations,” PHMSA wrote Nov. 1 in a letter to Chevron president Rebecca B. Roberts.  The letter listed four types of “probable violations.”

Right-of-Way Inspection

Chevron was using aerial patrols to inspect surface conditions around the pipeline’s Right-of-Way, even though the ROW “had areas of excessive overgrowth” and nearby structures that blocked the pipeline from view. Furthermore, a marker for a second pipeline was buried in the bushes, the agency said.

Aerial patrols thus “could not be used to adequately assess the surface conditions on or adjacent to the pipeline right-of-way” and inspections “should have been done by land vehicle or on foot,” the agency said.

This violation carried a fine of $45,400.

Corrosion Protection

Chevron did not follow its own procedures for controlling corrosion and otherwise protecting the pipeline systems against nearby electrical charges. Pipelines at risk of fault currents, lightning, and electrical arcing are required to have grounding devices. Chevron had no measures or devices in place to control corrosion or protect its pipelines, which ran beneath an electrical substation and near high-voltage electric transmission lines.

The investigation determined the failure was probably caused by a discharge of electric current onto the pipeline. The pipeline that failed was not protected or insulated from fault currents that could be imparted from the nearby transfer station. This “resulted in a hole being created in the pipeline due to electrical arcing from the facility fence pole,” the agency concluded.

These violations carried a fine of $316,600.

Leak Detection

Chevron did not have adequate means to detect leaks on the pipeline when it failed, allowing more than 10 hours to elapse before the local fire department noticed the release and notified the company, the agency said. Moreover, Chevron knew that its chosen method of leak detection was inadequate. The company’s own evaluation of the system in 2007 indicated that improvements were needed, but they were never made.

This violation carried a fine of $61,600.

Pipeline Clearance

Finally, the post of the fence that transferred the electrical charge was installed within three inches of the pipeline, despite a requirement that any underground pipe have at least 12 inches of clearance from any other underground structure. Exceptions are allowed if adequate provisions are made for corrosion control, but none were in place here, the agency said.

Chevron was not fined for this violation but was ordered to promptly correct it or face additional penalties.

"PHMSA's pipeline safety inspectors and its state partners are committed to ensuring the safety of America's pipeline transportation system, and will continue to carefully monitor the activities of Chevron Pipe Line Company," said PHMSA Administrator Cynthia L. Quarterman. "PHMSA will pursue enforcement action against operators that do not adhere to pipeline safety regulations."

Compliance Order Issued

In addition to the Notice of Proposed Violation, PHMSA issued a proposed Compliance Order that would require the company to improve its rights-of-way inspections, take measures to protect its system against damage from lightning or stray electrical currents; and improve its leak detection capabilities. Chevron can voluntarily take these actions before the order is finalized.

Pipeline operators are allowed up to 30 days to respond to allegations included in an NOPV. The company had no immediate comment on the PSMSA findings.

Houston-based Chevron Pipe Line Co. is a subsidiary of Chevron. The pipe line company’s network of approximately 10,800 miles of pipe reach nearly 2.2 million barrels and 1.4 billion cubic feet (Bcf) of natural gas on a daily basis, as well as additional volumes through joint ventures with other companies, the company says.

Chevron’s clean-up plan for the Red Butte Canyon spill can be found at http://www.chevron-pipeline.com/redbuttecanyonspill/.

   

Tagged categories: Corrosion; Pipeline; Pipelines; Violations

Comment Join the Conversation:

Sign in to our community to add your comments.

LS Industries
LS Blasters: Optimum Steel Cleaning Efficiency

Simplify surface prep with the precise shot control of LS Blasters. Our blast technology delivers optimum coverage and finish. 800-533-8008


Termarust Technologies
Termarust (HR CSA) Chemically Stops
Active Corrosion

Pipeline Utility Aerial crossings coated since 1992. Termarust's (HR CSA) was used to overcoat lead paint and preserve cables, pipes and support towers.


U.S. Zinc

Combat deterioration and corrosion with our zinc dust in your paints and coatings. U.S. Zinc – Helping the world work™


DeFelsko Corporation
PosiTector Dew Point Meter

Measures and records
environmental conditions
during surface prep and
painting. 4 Models
Available – Standard
or Advanced features,
Built-in or Separate probe.


BASF
New resins from BASF will have metals loving water:

Excellent corrosion resistance, low VOC, high gloss, thin films basf.us/industrialcoatings
polyorders@basf.com
800-231-7868


CS Unitec
Peening Preparation Tools

CS Unitec’s hand-held scarifiers are an ideal alternative to small-area shot blasting for cleaning and preparing concrete & metal surfaces. info@csunitec.com


CESCO
PRESSURE WASHERS

• 10,000 PSI
• Electric or diesel models
• Buy or rent from CESCO
• Lease Financing Available
CESCO is your One Stop
Corrosion
Shop
Contact us: 888-772-3726
BlastandPaint.com

 
 
 
Technology Publishing

The Technology Publishing Network

The Journal of Protective Coatings & Linings (JPCL) PaintSquare
Durability + Design Paint BidTracker JPCL Europe

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy policy   |   Terms & conditions   |   Site Map   |   Search   |   Contact Us
 

© Copyright 2000-2014, Technology Publishing / PaintSquare, All rights reserved
2100 Wharton Street, Suite 310, Pittsburgh PA 15203-1951; Tel 1-412-431-8300; Fax 1-412-431-5428; E-mail webmaster@paintsquare.com