Seattle’s Giant Borer Breaks Through

Thursday, April 6, 2017

More items for Program/Project Management
More items from North America

Comment | More

After nearly four years (with a few delays along the way), "Bertha," Seattle’s giant tunnel-borer, has broken through to the other side, completing its 9,270-foot journey under the city.

Bertha, the world’s largest tunneling machine, was built by Japanese manufacturer Hitachi Zosen, and has been operated by Seattle Tunnel Partners, the design-build contractor overseeing the Alaskan Way Viaduct Replacement Program. The machine broke through at the tunnel’s north end on Tuesday morning (April 4).

The project will replace the Alaskan Way Viaduct—a stretch of SR 99 in the city that is subject to risk from seismic activity—with a new route that includes a nearly 2-mile-long tunnel. The project began after the 1950s-era viaduct structure sustained damage from a 6.8-magnitude earthquake in 2001.

Bertha’s Breakdown

The borer began its journey in July 2013, but Bertha’s wheels came grinding to a halt that December after about 1,000 feet of tunneling. At first, officials thought it had been impeded by a steel pipe, an assertion STP still holds. But government officials have since argued that dirt had gotten into a bearing, unrelated to any pipe in the way, overheating the machine and damaging its seal system. Hitachi Zosan had to remove the machine and perform repairs that took nearly two years.

Once Bertha got going again in December 2015, it made quick progress, covering 8,000 feet in 15 months, with only minimal stops for maintenance and rest.

Legal Fights

The project—which, overall, is slated to cost about $3.14 billion—has been fraught with legal wrangling, especially in the wake of Bertha’s 2013 breakdown. STP, the state of Washington and the city of Seattle have dueling lawsuits pending, worth hundreds of millions of dollars.

STP’s suit against the state claims that an abandoned pipe caused the breakdown, and seeks damages of $480 million related to the repairs to the machine and time lost during the two-year fix time. The city of Seattle is suing STP for $81 million related to damage incurred because of sinking in the city’s Pioneer Square area, which the city says stems from groundwater removal related to the tunnel.

How Bertha Did It

Bertha, with a diameter of 57 feet, was designed specifically for the ground conditions under Seattle, according to the Washington State Department of Transportation. As the borer moved, it pulled pieces of precast concrete into place behind it, creating the tunnel structure. Crews have been working in the areas further back, creating the double-deck roadway inside it.

Bertha
Photos: WSDOT

As the borer moved, it pulled pieces of precast concrete into place behind it, creating the tunnel structure.

Some maintenance work involving the removal of cutting tools from the head of the borer had to be done in hyperbaric conditions, according to WSDOT, requiring crews to seal up the ground in front of Bertha with bentonite clay, then overpressurize the work area with compressed air.

Now that its mission is complete, the Seattle Times reports, Bertha will be almost entirely scrapped and melted down for reuse. The only parts eligible for recycling as-is, the paper says, are “generic parts such as hoses, belts, wires.”

Project Components

The 2-mile tunnel created by Bertha will connect at its south end with a 1-mile stretch of highway and an overpass that will guide vehicles over train traffic south of the tunnel. As part of the project, an off-ramp is being constructed of materials touted as "earthquake-proof," including rebar made of a nickel-titanium shape-memory alloy that returns to its original form after being stressed.

Earthquake-proof off-ramp

An off-ramp is being constructed of materials touted as "earthquake-proof," including rebar made of a nickel-titanium shape-memory alloy that returns to its original form after being stressed.

The Alaskan Way Viaduct will be demolished as part of the project, and a new surface street along the waterfront will be created, along with a waterfront park.

The $3 billion bill for the job is being footed largely by state gas taxes, along with other state funding. The Federal Highway Administration is contributing $787 million, and the local government and Port of Seattle have chipped in as well.

The tunnel will be tolled, which will account for $200 million of the construction costs, per the Washington legislature. Future tolls will also be used for maintenance of the tunnel once it is in use.

The tunnel is expected to open by the beginning of 2019, more than four years later than its original intended completion date.

   

Tagged categories: Contractors; Federal Highway Administration (FHWA); Infrastructure; Roads/Highways; Tunnel

Comment Join the Conversation:

Sign in to our community to add your comments.

Advertisements
 
Detail Masters
 
Overspray Removal
 
We offer professional, turnkey service and unparalleled quality!
Our process can save hundreds— even thousands of dollars. It's fast, environmentally safe and 100% guaranteed.
 

 
SABRE Autonomous Solutions
 
Quality
 
The ALPHA1 provides a consistent finish day-in
day-out; job to job.
 

 
SEMicro Division, M.E. Taylor Engineering, Inc.
 
Coatings Adhesion Testers
 
The PATTI® accurately measures the bond strength between coating & substrate. Outfitted properly, the surface can be rough, porous, or curved & >10K psi strong!
 

 
SAFE Systems, Inc.
 
Portable Dust Collectors for Tough Environments
 
Trailer and skid-mounted models in numerous sizes, powered by electric and/or diesel. Sloped roofs, multiple dust inlets, high static, dampered fans. Lockable power & drive compartments.
 

 
Clemco Industries Corp.
 
Maximum Dust Suppression Systems Start at $14,950
 
The system comprises proven technology and equipment with user-friendly flexibility in mind. See it in action.
 

 
W Abrasives
 
How to reduce your blasting cost ?
 
W Abrasives is able to reduce the global blasting cost to its customers by offering specific ranges of products and technical support dedicated to their application.
 

 
SSPC: The Society for Protective Coatings
 
http://www.sspc.org/
 
Join SSPC and Enhance
Your Career !
 

 
Safway Services
 
Safeguard Assets. Ensure Productivity. HAKI®
 
Protect assets and equipment. Keep facilities open and operational. Maintain schedules regardless of weather. Ensure smooth and continuous production. Easy to erect. Safway is the primary distributor of HAKI® products including HAKISPAN and HAKITEC® 750 – in North America.
 

 
PPG Protective and Marine Coatings Group
 
We Protect and Beautify the World
 
PPG is widely recognized as a world leader in protective and marine coatings, developing innovative, cutting-edge products and services.
 

 
Aggreko
 
Dehumidification, Power and Temperature Control Rentals
 
Aggreko offers rental solutions for your painting/coating project. Dehumidifiers, cooling, heating, power and 24/7 service, nationwide.
844-433-9802
 

 
 
 

Technology Publishing Co., 1501 Reedsdale Street, Suite 2008, Pittsburgh, PA 15233

TEL 1-412-431-8300  • FAX  1-412-431-5428  •  EMAIL webmaster@paintsquare.com


The Technology Publishing Network

Durability + Design PaintSquare the Journal of Protective Coatings & Linings Paint BidTracker

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy policy   |   Terms & conditions   |   Site Map   |   Search   |   Contact Us