Vibrations Shake Off Paint in Ship Test

Friday, June 6, 2014

More items for Program/Project Management

Comment | More

Operator error is being blamed for paint and electrical damage on a brand-new, $1.5 billion Australian Navy ship—blame that the operator is strongly disputing.

A civilian contract crew was conducting a sea trial between Melbourne and Sydney of the Royal Australian Navy's NUSHIP Canberra (III) when the hull was damaged and its electrical system melted down, The Daily Telegraph reported.

The vessel, built by contractors BAE Systems Australia and Navantia, is the first of two $1.5 billion, 27,000-tonne, 231-meter-long Amphibious Assault Ships, also known as a Landing Helicopter Docks.

NUSHIP Canberra
Royal Australian Navy / LSIS Helen Frank

Vibrations during the sea trial of the $1.5 billion NUSHIP Canberra damaged some of the ship's coatings. The problem has been blamed on a civilian contract crew, according to media reports.

The Canberra class consists of the largest ships ever built for the RAN.

Bad Vibrations

According to media reports, a civilian crew from Teekay Shipping Corp. hired by BAE Systems Australia was testing the ship's performance in May when operator error caused the vessel to vibrate and damage the hull.

The problem was linked to the ship's two propulsion pods, also called azimuth thrusters, that were out of alignment, causing vibrations, the reports said.

Each of the thrusters has two propellers that can be rotated to any angle. However, the civilian crew "was apparently unaware that the pods must be operated in tandem above eight knots," local news outlets reported.

Instead, the crew ran them separately in low-speed mode while at high speed, setting off serious vibrations throughout the ship.

Fun House

"It was like the shaking floor in an amusement park house of fun," a project source said, according to The Daily Telegraph.

While damage to the structure was minimal, the shaking caused paint to be stripped from the ship's hull in the area above the pods.

The newspaper cited a project source who called the problem an "operator error" and reported that the vibration stopped once the pods were back in the correct mode.

Corrosion, Cracks Spotted

But problems with the ship didn't end there. The crew reportedly lost steering capabilites after an electrical power failure and had to drop anchor for four hours.

BAE Systems
Royal Australian Navy

The Canberra-class ships were built by first constructing 112 individual modules and then welding them together.

According to The Daily Telegraph, this issue was also attributable to the crew, who "forgot to disconnect the emergency power," causing the circuit breakers to melt when the main power came back on.

Additionally, "excessive" corrosion was discovered in propeller nuts and a crack was found in the ship's hull, which was said to have occurred during shipment from Spain.

Despite the list of problems, the project source told the newspaper, "The trial didn't go as well as hoped, but it was better than expected."

Staff Negligence 'False'

A spokesperson for Teekay Shipping Australia denied that the ship's problems resulted from crew errors, according to Dailymail.co.uk.

"[C]laims that the hull of the HMAS Canberra was damaged and that an electrical system melted down are fallacious. The claim that Teekay seastaff were negligent resulting in damage to the vessel is completely false," the spokesperson said.

BAE Systems announced plans to start sea trials in March. These will take the ship from Williamstown to Sydney, where it will be drydocked to have the hull cleaned before final paint application and the deck painted.

BAE Systems did not immediately respond to a request for comment Thursday (June 5).

The Canberra is expected to have a second sea trial in July before RAN takes control of the ship.

Piece-by-Piece Shipbuilding

BAE Systems and Navantia built the ships using a modular approach; the ships were divided into 112 modules that were built and fitted out as discrete units and then welded together. This method allows the ship to be built at several different sites throughout the shipyard, the RAN explained.

The vessels have a conventional mono steel hull design with the superstructure located on the starboard side of the flight deck.

Construction of the hull to the level of the flight deck and the majority of the fitting out was done at Navantia's shipyard in Ferrol, Spain.

The consolidation of the superstructure and installation of the combat and communication systems were done at BAE Systems' shipyard in Williamstown, Victoria.

 

   

Tagged categories: Coating failure; Contractors; Shipyards

Comment from Mark Edmonds, (6/6/2014, 6:48 PM)

A few years ago the US Coast Guard had a new ice breaker on the Great Lakes built with azipod propulsion. In a very short time the coating aft of the azipods had been stripped off, ostensibly from the cavitation of the azipods. The coating that was stripped off was an elastomeric ice breaking resistant product and it still came off. Another instance now of coating coming off on an azipod propelled vessel seems more than coincidence, even though I am feel there are vessels in operation with azipods that are performing as expected.


Comment from peter gibson, (6/9/2014, 5:24 PM)

Article says coating disbonded from vibration... is that possible ?


Comment from M. Halliwell, (6/10/2014, 10:06 AM)

I don't know if it would be a vibration itself, Peter...but rather that the vibration was a symptom of what else was going on. Localized cavitation at the azipods due to a misalignment could generate a nasty enough waterhammer to pound the coating off the hull and feel like a vibration within the ship.


Comment Join the Conversation:

Sign in to our community to add your comments.

SAFE Systems, Inc.
Enduroguard -
The Tough Cable
for a Tough Industry.

Reduce maintenance costs and down time, increase job site safety with Enduroguard Cable. Available exclusively from SAFE Systems. UL listed, flexible, abrasion resistant and cut resistant.


Minerals Research & Recovery

HIGH PERFORMANCE ABRASIVES


“Made in the USA!”

Why recycle waste from other countries? Go FASTER, CLEANER, at 1/3 THE COST with MR&R “All-American” Sharpshot®HP!!

WATCH THE VIDEO


Clemco Industries Corp.
Powerful Protection in a Small Package

Mounts inside blast helmet, alerts operator to dangerous breathing-air condition by audible, visual, and vibratory alarms. Easily calibrated, battery operated.


Barton International
Garnet Abrasives result in Shorter Blast Times

Get your customers back on line fast with Barton engineered garnet abrasives. 2 to 4 times harder and up to 2 times heavier than ordinary abrasives. Call 800-741-7756 or Email info@barton.com


SSPC: The Society for Protective Coatings
http://www.sspc.org/

Join SSPC and Enhance
Your Career !


DeHumidification Technologies
HUMIDITY PROBLEMS?

DH Tech has the most innovative and reliable equipment available to
control humidity efficiently
and effectively.
IT'S UNDER CONTROL!


Atlantic Design, Inc.
POWER ON WITH ADI!

The most air flow possible… In the smallest package imaginable… For a price you won’t believe! 866.Call.ADI

 
 
 
Technology Publishing

The Technology Publishing Network

The Journal of Protective Coatings & Linings (JPCL) PaintSquare
Durability + Design Paint BidTracker JPCL Europe

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy policy   |   Terms & conditions   |   Site Map   |   Search   |   Contact Us
 

© Copyright 2000-2014, Technology Publishing / PaintSquare, All rights reserved
2100 Wharton Street, Suite 310, Pittsburgh PA 15203-1951; Tel 1-412-431-8300; Fax 1-412-431-5428; E-mail webmaster@paintsquare.com