PaintSquare.com


The First Word in Protective & Marine Coatings

A Product of Technology Publishing / PaintSquare
JPCL | PaintSquare News | Durability + Design | Paint BidTracker

Free Download of

Paint and Coatings Industry News

Main News Page


100-Foot Span Slides into Place

Thursday, March 27, 2014

More items for Program/Project Management

Comment | More

Progress on the new $103 million Milton-Madison Bridge project is sliding steadily forward—if, occasionally, in sideways fashion.

The novel project is being built in the same footprint as the existing 85-year-old bridge, using design and construction methods called "superstructure replacement" and "truss sliding."

Construction Innovation

With superstructure replacement, the existing piers are widened, strengthened and then reused.

Milton-Madison Bridge
Images, video: www.miltonmadisonbridge.com

Crews jacked a corner of the bridge over the weekend to replace a slipped bearing.

With truss sliding, as the name suggests, the new superstructure is built on steel piers adjacent to the existing bridge. Then, using computer-controlled hydraulic jacks, the new superstructure is pulled across steel beams into place on top of the renovated existing piers. The downstream piers are then removed.

While the truss slide method has been used occasionally, Madison-Milton Bridge project officials says this is the longest such project ever undertaken in the U.S. The new Milton-Madison main truss is 2,428 feet long and 40 feet wide.

Project officials say the design-build innovations will cut years from the project schedule and reduce the overall cost by 20 percent. Indeed, the new bridge is already open to traffic on temporary piers.

The Little Slide

Last week, general contractor Walsh Construction successfully slid a 100-foot concrete approach into place on the massive structure, which will connect Milton, KY, with Madison, IN, over the Ohio River.

Time-lapse video reduces the two-hour sliding installation of a 100-foot concrete approach to one minute.

The approximately two-hour project on March 13, reduced to about one minute via time-lapse video, was a critical precursor to sliding the bridge's nearly half-mile steel truss into place—possibly as soon as next week, authorities say.

The main truss slide will use the same equipment and process as the approach slide over the Kentucky riverbank.

Bearing Project

The concrete approach slide followed a project to replace a five-foot-square steel truss bearing that dislodged March 11 as crews were installing sliding harnesses on the bridge.

The concrete slide was completed, but crews began a 15-hour jacking process on Friday afternoon (March 21) to raise the bridge's southeast corner nearly one foot to slide the bearing back into place.

Milton-Madison bearing replacement

A five-foot-square steel bearing was replaced last weekend after it dislodged while crews were installing harnesses for the upcoming truss slide.

By 6 a.m. Saturday (March 22), the jacks were removed and the bridge load was back on its bearings.

“The jacking process went as expected,” said Dav Kessinger, project manager for Kentucky Transportation Cabinet, which is overseeing the project with the Indiana Department of Transportation. “With this work completed, the focus is now on preparations for sliding the main truss.”

The Big Slide

The steel truss will be moved 55 feet onto the permanent piers, closing the bridge for one week. The bridge will remain closed while crews pour concrete, install expansion joints, stripe pavement and complete the connection of the bridge to the permanent approaches.

MM Bridge jacking Dav Kessinger

Four jacks, each able to lift 250 tons, were used to raise the southeast corner of the bridge March 22—a process that "went as expected,” said Dav Kessinger (right), project manager for Kentucky Transportation Cabinet.

In all, project officials expect to be able to limit the bridge closure to just 10 days of the project—a fraction of the year-long closure originally anticipated.

Construction updates, including a live web cam, are available on the project site.

   

Tagged categories: Bridges; Construction; Design; Government contracts; Infrastructure; Walsh Construction

Comment Join the Conversation:

Sign in to our community to add your comments.

Minerals Research & Recovery

HIGH PERFORMANCE ABRASIVES


“Made in the USA!”

Why recycle waste from other countries? Go FASTER, CLEANER, at 1/3 THE COST with MR&R “All-American” Sharpshot®HP!!

WATCH THE VIDEO


SAFE Systems, Inc.
Portable Dust Collectors for Tough Environments

Trailer and skid-mounted models in numerous sizes, powered by electric and/or diesel. Sloped roofs, multiple dust inlets, high static, dampered fans. Lockable power & drive compartments.


Surface Prep Supply
Surface Prep Supply

Blast It! Coat It! We have you covered every step of the way. Supplier of:
• Abrasives
• Equipment
• Accessories
• Protective Coatings
888-331-7737(PREP)


LS Industries
LS Blasters: Optimum Steel Cleaning Efficiency

Simplify surface prep with the precise shot control of LS Blasters. Our blast technology delivers optimum coverage and finish. 800-533-8008


Termarust Technologies
Termarust (HR CSA) Chemically Stops
Active Corrosion

Truss bridge treated in 2000 with Termarust's (HR CSA) field-proven rust mitigation system chemically stopped corrosion, crevice corrosion & pack rust.


Safway Services
One Source. Every Solution.

The Safway Group is your source for multiservices. Painting, coating, insulation and more – all from the most trusted name in the industry.


Wasser High-Tech Coatings Inc.
Wasser Coatings Protect

some of the most important bridges in the country; learn about our NEPCOAT-approved system and our entire range of MCU & Polyurea coatings. 1-800-627-2968 www.wassercoatings.com

 
 
 
Technology Publishing

The Technology Publishing Network

The Journal of Protective Coatings & Linings (JPCL) PaintSquare
Durability + Design Paint BidTracker JPCL Europe

 
EXPLORE:      JPCL   |   PaintSquare News   |   Interact   |   Buying Guides   |   Webinars   |   Resources   |   Classifieds
REGISTER AND SUBSCRIBE:      Free PaintSquare Registration   |   Subscribe to JPCL   |   Subscribe to PaintSquare News
MORE:      About PaintSquare.com   |   Privacy policy   |   Terms & conditions   |   Site Map   |   Search   |   Contact Us
 

© Copyright 2000-2014, Technology Publishing / PaintSquare, All rights reserved
2100 Wharton Street, Suite 310, Pittsburgh PA 15203-1951; Tel 1-412-431-8300; Fax 1-412-431-5428; E-mail webmaster@paintsquare.com